Novo Confirms Delivery of Steinert KSS Mechanical Sorter and Provides Operational Update From Beatons Creek
December 08 2020 - 9:15AM
Novo Resources Corp. (“
Novo” or
the “
Company”) (TSX-V: NVO & NVO.WT; OTCQX:
NSRPF) is pleased to announce it has taken delivery of its Steinert
KSS mechanical sorter and provides an operational update from its
Beatons Creek gold project (“
Beatons Creek”) and
Nullagine processing facility (
“Golden Eagle
Mill”).
Mechanical
Sorting
Update:
- The Steinert KSS mechanical sorter has
arrived into the port of Fremantle (Perth) and is currently being
delivered to Steinert’s test facility;
- Orders have been placed for all long
lead items (feeder hopper, feeder conveyor, discharge conveyors).
Pre-assembly will occur at Steinert / OPS facility in Bibra Lake
(Perth) prior to mobilization to site;
- Planning is well advanced with design
of support infrastructure – compressed air, power, cyclone rated
shelter / offices; and
- The Comet Well / Purdy’s Reward
mechanical sorting trial remains on track to commence in April 2021
subject to receiving requisite approvals from the Department of
Mines, Industry Regulation, and Safety and the Department of Water
and Environmental Regulation. Ngarluma Aboriginal Corporation
approval has been granted.
Beatons Creek and Nullagine Gold Project
Update:
Development at Beatons Creek and refurbishment at
the Golden Eagle Mill continue to progress safely, on schedule and
within budget. Recent key milestones achieved include:
- Mining contractor systems alignment
and pre-mobilization works proceeding to plan to support arrival of
first plant and personnel from December 14th;
- Grade control drilling now operating
day and night shifts as planned; and
- Site personnel (including contractors)
now totaling 80.
Please see the Company’s news release dated
November 18, 2020 for the Company’s previous operational
update.
Mining
Contractor Mobilization:
- Senior Iron Mine Contracting Pty Ltd
(“IMCPL”) personnel have attended site post
contract award and are in advanced stages of planning to support
the arrival of first plant and equipment from December 14th.
Development activities at Beatons
Creek:
Grade control program:
- Grade control reverse circulation
drilling by Castle Drilling continues to progress well across the
Edwards and Grant’s Hill areas, with high density drilling underway
(10m x 10m drill hole spacing and 0.5m sample interval) (see figure
1);
- Grade control drilling has now shifted
to day and night shifts as planned to accelerate works ahead of
mining; and
- Sample dispatches continue to be
transported to MinAnalytical in Kalgoorlie for gold
PhotonAssay.
Mine development works
- Australian Aboriginal Heritage Act
Section 18 removal and relocation of Aboriginal artefacts from
around the Grant’s Hill area completely successfully under the
supervision of custodians of the land at Beatons Creek;
- Topsoil stripping of Grant’s Hill
waste dump location has commenced (see figure 2);
- Office and laydown pads have been
established at Beatons Creek, with office buildings being relocated
from the Golden Eagle Mill location commencing on December 10,
2020; and
- Lacy Contracting Services P/L have
been retained to conduct preliminary haulage works from Beatons
Creek to the Golden Eagle Mill, with haulage starting immediately
with a single truck to relocate historical stockpiles of ore to the
Golden Eagle ROM pad.
Refurbishment works on
the Golden Eagle
Mill:
Plant refurbishment:
- Works continue with refurbished key
componentry returning from Perth for installation – all continues
according to schedule;
- Work in the leach tanks and launders
continues to plan, with 6 tanks fully refurbished ahead of
reinstallation of trash screens, carbon pumps and agitators, with
refurbishment works in the remaining 3 tanks due for completion
prior to year’s end (see figure 3); and
- Burgess BLA (specialist mill
contractors) have attended site to inspect all operational aspects
of the mill, including alignment, motor, gearbox, girth gear,
pinion, lubrication systems and feed and discharge end bearings.
Bearings and girth gear have been assessed and ready for
operations. Seals have been replaced with final components being
manufactured in Kalgoorlie, Western Australia ready for
installation next month. Final motor and gearbox alignment will be
undertaken immediately prior to commissioning in mid-January
2021.
Civil works:Foundations have now been completed for
the upgraded Acacia reactor unit along with new elution tank
footings in the gold room. The mining contractor’s workshop slab is
nearing completion. The GR Engineering Services
(“GRES”) scope currently stands at approximately
50% complete, with works continuing on schedule and within budget
with no material issues or problems encountered thus far.
Long lead items have all been ordered and arrival
dates remain within the refurbishment schedule.
Other
major tenders:
- A 3-year camp management and catering
services contract has been awarded to Cater Care Services P/L.
Cater Care’s experience as the previous camp operator stands them
in good stead for delivering an excellent service at the site;
and
- The permanent surface haulage contract
package is out for tender, with solid progress being made with
numerous other commercial agreements for fuel supply, processing
reagents, assay laboratory services and flights.
Novo CEO and director Rob Humphryson commented,
“GRES and their key subcontractors Duratech P/L and Northfields WA
P/L continue to perform outstanding work. The further we move
through plant refurbishment works without encountering major
operational issues, the more we de-risk the start-up and
commissioning phases of the project. On the people front, Novo is
assembling an outstanding team across all facets of the operation,
with observable levels of enthusiasm, commitment and communication
auguring well for the future success of the operation.”
Dr. Quinton Hennigh (P.Geo.) is the qualified
person pursuant to NI 43-101 responsible for, and having reviewed
and approved, the technical information contained in this news
release. Dr. Hennigh is President, Chairman, and a director of
Novo.
About Novo Resources Corp.
Novo is advancing its flagship Beatons Creek gold
project to production while exploring and developing its highly
prospective land package covering approximately 14,000 square
kilometres in the Pilbara region of Western Australia. In addition
to the Company’s primary focus, Novo seeks to leverage its internal
geological expertise to deliver value-accretive opportunities to
its shareholders. For more information, please contact Leo
Karabelas at (416) 543-3120 or
e-mail leo@novoresources.com
On Behalf of the Board of Directors,
Novo Resources Corp.
“Quinton Hennigh”Quinton Hennigh President and
Chairman
Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of the
TSX Venture Exchange) accepts responsibility for the adequacy or
accuracy of this news release.
Forward-looking information
Some statements in this news release contain
forward-looking information (within the meaning of Canadian
securities legislation) including, without limitation, the
successful completion of development and plant refurbishments works
on time and on budget, and that Novo’s board of directors will make
the decision to commence full-scale production at Beatons Creek.
Forward-looking statements address future events and conditions
and, as such, involve known and unknown risks, uncertainties and
other factors which may cause the actual results, performance or
achievements to be materially different from any future results,
performance or achievements expressed or implied by the statements.
Such factors include, without limitation, the successful completion
of site establishment works at Beatons Creek, the successful
completion of grade control drilling works, MinAnalytical’s ability
to assay the Company’s drill samples in a timely and cost-effective
manner, the successful completion of mining, camp management, fuel
supply, processing reagents, assay laboratory services, flights,
and haulage services contracts, and customary risks of the resource
industry.
PDFs accompanying this announcement are available
at:
http://ml.globenewswire.com/Resource/Download/05c34327-f38f-4cd9-af79-319b3d9ab801
http://ml.globenewswire.com/Resource/Download/6a50caa0-a002-4dca-a96c-81f7fb3dc7e7
http://ml.globenewswire.com/Resource/Download/59e03b17-bb22-4454-b3df-f57704e1309f
Novo Resources (TSXV:NVO)
Historical Stock Chart
From Dec 2024 to Jan 2025
Novo Resources (TSXV:NVO)
Historical Stock Chart
From Jan 2024 to Jan 2025