VANCOUVER, BC,
June 15,
2022 /CNW/ - Cypress Development Corp. (TSXV:
CYP) (OTCQX: CYDVF) (Frankfurt: C1Z1) ("Cypress" or "the
Company") is pleased to provide an update on the progress of the
ongoing Feasibility Study for the Company's Clayton Valley Lithium
Project, in Nevada, USA. The
Feasibility Study is under the direction of Wood PLC ("Wood") and
Global Resource Engineering ("GRE") and all related work is
proceeding well, and it remains on track for completion in late
2022.
Activity Highlights:
- Geotechnical study in progress
- Continued operation of the Pilot Plant
- 500-ton bulk sample collected for further metallurgical
material
- Sonic drill program completed consisting of 580 meters in eight
drill holes
- Resource model updated with data from recently acquired
property
Geotechnical Program
Wood personnel conducted on-site visits in supervising the
collection of geotechnical data for the foundation design of the
Company's processing plant site and tailings storage facility. The
samples collected for Wood's geotechnical program were shipped to
materials testing laboratories, and additional on-site work is
planned in the next month.
GRE personnel conducted site visits in preparation to work on
the Project's resources and reserves. GRE personnel supervised the
collection of a suite of large-diameter core samples for assay and
geotechnical testing, which will provide further information for
GRE's work on the mine design.
Lithium Extraction Facility
("Pilot Plant")
Testing continues at Cypress' Pilot Plant in Amargosa Valley, 100 miles southeast of the
Clayton Valley Lithium Project site. The Pilot Plant is now working
in its 12th cycle of continuous 24-hr per day testing.
The tests are ongoing to examine efficiencies in processing,
testing various configurations in equipment and operating
conditions, and the plant continues to produce concentrated lithium
solutions for use in downstream product testing.
Wood's process engineering team is working with Continental
Metallurgical Services and the data from the Pilot Plant, to
develop mass balance and equipment sizing. Wood's engineers are
also working on the overall project infrastructure, including
selection and design of access roads, plant equipment, power, and
water supplies.
Bulk Sample
To support continued testing, a 500-tonne sample of claystone
was excavated in late April from an engineered test-pit and
transported to the Company's operations headquarters at the
Tonopah airport, where it will be
crushed, screened, and bagged in preparation for treatment at the
Company's Pilot Plant. The sample was collected near DCH-1, and in
the vicinity of the planned starter-pit for mining in the
Feasibility Study.
"We are pleased with the bulk sampling work. The size of the
bulk sample may be larger than necessary for the Pilot Plant to
provide adequate information for the Feasibility Study" said
President and CEO Bill Willoughby.
"This sample, however, allows us to examine lithium grade and other
properties in the claystone over a larger volume. It also ensures
we have material on hand, should we need it, for future tests or
continued operations."
Sonic Drill Program
Cypress is continuing to log and sample core from a sonic drill
program which commenced and was completed in May. The purpose of
the drill program was to obtain large-diameter (6-inch) continuous
core. Eight locations were selected for metallurgical,
geotechnical, lithological purposes. Each hole yielded 1.9 to 2.3
tonnes of claystone which will be used in metallurgical testing at
the Company's Pilot Plant to examine if there are any variations in
performance due to depth, location, or material type in the
deposit.
Four of the holes (CSV-1 through CVS-4) were completed in the
central portion of the project in the vicinity of the proposed
starter-pit and the 500-tonne bulk sample. Four other holes
(CVS-5 through CVS-8) were completed in the northeast portion of
the project on and near the parcel of property recently acquired
from Enertopia Corporation ("Enertopia"). In addition to providing
metallurgical sample material, these latter four holes will provide
confirmation of the data from Enertopia's previous drilling.
"The drilling program proceeded better than expected and was
very successful in this first application of sonic drilling in
Clayton Valley" stated Daniel
Kalmbach, Cypress Manager, Geology and QP. "The quality of
the large-diameter core samples are excellent and will provide
further valuable data for the Feasibility Study."
Resource Model
The recent addition of land acquired from Enertopia (see news
release dated May 5, 2022)
resulted in the addition of five core holes which were drilled by
Enertopia in 2018. This property comprises 17 unpatented mining
claims totaling 160 contiguous acres immediately adjacent to
Cypress's Project. A March 2020 NI
43-101 compliant technical report (published by Enertopia) on the
property shows an Indicated resource of 82 million tonnes (mt) of
1,121 parts per million (ppm) Li and an Inferred resource of 18 mt
of 1,131 ppm Li using a cutoff grade of 400 ppm Li. Cypress has not
independently confirmed the resource indicated in the March 2020 NI 43-101 report.
All data received from the property acquisition has been
incorporated into the project database and is expected to be used
by GRE to generate the resource and reserve estimates and develop
the mine plan for the Feasibility Study
Qualified Person
Daniel Kalmbach, CPG, is the
qualified persons as defined by National Instrument 43-101 and have
approved of the technical information in this release.
About Cypress Development
Corp
Cypress Development Corp. is a Canadian based advanced stage
lithium company, focused on developing its 100%-owned Clayton
Valley Lithium Project in Nevada,
USA. Cypress is in the pilot stage of testing on material
from its lithium-bearing claystone deposit and progressing towards
completing a feasibility study and permitting, with the goal of
becoming a domestic producer of lithium for the growing electric
vehicle and battery storage market.
ON BEHALF OF CYPRESS DEVELOPMENT
CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES
PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE
CONTENT OF THIS NEWS RELEASE.
Cautionary Note Regarding
Forward-Looking Statements
This release includes certain statements that may be deemed
to be "forward-looking statements". Forward-looking statements
are subject to risks, uncertainties and assumptions and are
identified by words such as "expects," "estimates,"
"projects," "anticipates," "believes," "could," "scheduled," and
other similar words. All statements in this release, other
than statements of historical facts, that address events or
developments that management of the Company expects, are
forward-looking statements. Although management believes the
expectations expressed in such forward-looking statements are based
on reasonable assumptions, such statements are not guarantees of
future performance, and actual results or developments may differ
materially from those in the forward-looking statements. The
Company undertakes no obligation to update these forward-looking
statements if management's beliefs, estimates or opinions, or other
factors, should change. Factors that could cause actual results to
differ materially from those in forward-looking statements, include
market prices, exploration, and development successes, continued
availability of capital and financing, and general economic, market
or business conditions. Please see the public filings of the
Company at www.sedar.com for further information.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/cypress-development-progress-on-feasibility-study-301568346.html
SOURCE Cypress Development Corp.