said on Sept. 21
Valero McKee TX 170.0 Expansion project announced
March 2011 to increase crude oil
throughput by 25,000 b/d to
195,000 b/d.
Valero Norco, LA 185.0 Hydrocracker project will 2013
finish in first quarter of 2013
and commence operating in the
second quarter, company said
on Oct. 10.
Upgrade project to build 2012
a new diesel hydrotreater
unit moved from 2010 to
4Q 2012.
Valero Port Arthur 325.0 Hydrocracker project will pro- Late
TX ceed and be completed in late 2012
2012.
MIDWEST
BP Whiting, IN 336.0 Largest of 3 CDUs will shut in Late
late in 4Q 2012 for expansion 4Q
project, the co. said July 31. 2012
Project completion set 2nd-half
2013.
BP/Husky Toledo, OH 160.0 Refinery will be at planned rates
Oct. 12 after a month of maintenance Oct 11
at FCCU and coker compressors ended.
CVR Wynnewood 54.0 Turnaround work still under way
Energy OK the co. said on Oct. 11. The
work resumed Sep 30 after Sep 29
boiler explosion. No other process
units affected by the blast.
30-40 days maintenance in Q3 2012
announced on Nov. 3, 2011.
Holly Tulsa, OK 125.0 The entire refinery will be shut Late
Frontier while West Plant section under- 2012
goes major turnaround maintenance
in late 2012, the Co. said on
Aug. 5, 2011.
Holly El Dorado 139.0 Coker unit undergoing maintenance
Frontier KS until further notice, traders said
on Sep 14. No significant impact
to production is expected.
Husky Lima, OH 160.0 30-day maintenance will begin Sept
Energy in Sept. the Co. said on July 24. 2012
Scope of work not disclosed.
15-day maintenance planned at 4Q
diesel hydrotreater; 29-days at 2012
aromatics unit, set for 4Q 2012,
the Co. said on Feb 9, 2012.
New 20,000-b/d kerosene hydro- 1stH
treater will start up in 1st 2013
half 2013, to co. said on Feb 9,
2012.
45-days of major turnaround
scheduled in 2014; 70% of units
involved. Remaining 30% will under
go major turnaround in 2015, the
co. said on Feb 9, 2012.
Phillips Roxana, IL 305.0 Unspecified unit shut for planned
66 maintenance on Sep 25, the co.
said. No further details provided.
ROCKIES
WEST COAST
Phillips Rodeo, CA 80.0 Planned maintenance is under way
the co. said on Oct. 4. No further
details provided.
Tesoro Martinez, CA 166.0 Reformer restart began Sep 23
after Sep 16 shutdown reports
to regulators said.
Copyright (c) 2012 Dow Jones & Company, Inc.