The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Citgo Petroleum Corp.'s refinery in Corpus Christi, Texas, reported Thursday that an FCCU at the East Plant was being restarted.

Valero Energy Corp.(VLO) said Thursday that the hydrocracker at its Port Arthur refinery was operating at normal rates after a brief upset at a feed pump. A company spokesman also said that ice on a 66,000-b/d FCCU at Valero's Jean Gaulin refinery in Quebec, Canada, is delaying the ability to assess damages from a fire early Tuesday.

Marathon Oil Corp.'s (MRO) refinery in Catlettsburg, Ky., extinguished a fire that broke out Thursday morning at its idled lubricants plant, a spokeswoman said. The refinery has been operating at "somewhat reduced rates" due to a gate damaged at the Greenup Locks that has backed up barge traffic on the Ohio River.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
 
Operator   Refinery    Capacity   Description                  Restart 
                       (in 000s 
                       bbl/day) 
 
UNPLANNED 
 
CANADA 
 
Korean   Newfoundland  115.0   Hydrocracker was shut Jan. 7 
National                       after a brief fire broke out in 
Co.                            the stripper tower. No word on 
                               when it will restart, the co. 
                               said on Feb 2. 
 
Valero   Quebec City   235.0   66,000-b/d FCCU shut by early-   n/a 
         Quebec                day fire on Feb 2. Damage asses- 
                               ment underway, but delayed due to 
                               ice on unit; restart timing 
                               not yet known, Co. said Feb 4. 
CARIBBEAN 
 
EAST COAST 
 
GULF COAST 
 
Citgo    Corpus        163.0  Platformer reactor was shut after 
         Christi,TX           a brief fire Dec. 30. No injuries. 
                              Co. still assessing damages. 
 
Motiva   Norco, La.    236.4  Crude unit, DU-5, shut by fire    Early 
                              on Jan 22 seen restarting in      April 
                              early April, the Co. said on 
                              Feb 2. 
 
Motiva  Port Arthur    285.0  Crude oil throughput will soon    End 
                              return to normal rates the co.    Jan 
                              said on Jan 28; runs were re- 
                              duced due shipping delays caused 
                              by the closure of the Sabine- 
                              Neches Waterway, the co. said on 
                              Jan. 26. 
 
Valero  Port Arthur    325.0  Part of delayed coker unit no.    n/a 
        TX                    843 was depressurized for 
                              maintenance on Jan. 30. No 
                              impact to production. 
 
                              Hydrocracker returned to normal 
                              operations after a brief upset 
                              at feed pump, Co. said Feb. 4. 
 
Valero  Texas City     245.0  1 of 3 crude units was re-        Jan 28 
        TX                    started Jan 28; a fire on Dec 
                              24 shut the crude unit and a 
                              coker unit. The coker unit was 
                              restarted on Dec. 31. 
 
WRB     Borger, TX     152.0  Process upset occurred on         n/a 
Refining                      Jan 30 at FCCU and wet gas 
                              compressor causing brief 
                              period of flaring. Impact on 
                              production unclear. 
 
 
MIDWEST 
 
ROCKY MOUNTAINS 
 
Holly    Artesia,      100.0  A fire erupted Jan. 18 at crude   early 
         N.M.                 unit; restart seen in 3 weeks.    Feb 
 
Marathon Catlettsburg  226.0  Refinery operating at reduced     n/a 
         KY                   rates owing to the closure 
                              since Jan 27 of the Ohio River 
                              due to damage at the Greenup 
                              Locks and Dam. Traffic was 
                              restarted Jan. 31 but has been 
                              slow moving, Co. said Feb. 4. 
 
                              Small fire broke out at an idled 
                              lubricants plant Feb. 4; no impact. 
 
WEST COAST 
 
Conoco   Wilmington    139.0  Flaring reported on Feb 2 at 
         CA                   unspecified unit(s) for un- 
                              known reason; investigation 
                              underway. Impact to production 
                              unclear. 
 
Shell    Martinez     155.6   Delayed coker unit caused steam   n/a 
         CA                   and coke dust emissions Jan. 27; 
                              cause is unknown. No impact on 
                              production. 
 
PLANNED 
 
CANADA 
 
Shell    Montreal     130.0   The refinery will be converted 
         Quebec               into a fuel terminal, Co. said 
                              Jan. 7. No timeline provided. 
 
 
CARIBBEAN 
 
Hovensa  St. Croix    500.0   150,000 bbl/d FCCU shut           early 
                              Jan. 20 for turnaround.           March 
 
Valero   Aruba        235.0   The plant, which 
                              was shut in June for 2-3 
                              months for economic reasons was 
                              closed indefinitely in Nov. 
 
EAST COAST 
 
Conoco   Linden, NJ    238.0  Refinery operating at planned 
                              rates, following turnaround 
                              maintenance at the plant's 
                              140,000-b/d FCCU since early 
                              Jan, a person familiar with 
                              the plant said on Feb 2. 
 
Hess     Port                 Month-long turnaround work 
         Reading NJ           will take place in April at 
                              the plant's 70,000-b/d 
                              FCCU; the refinery does not 
                              process crude oil. 
 
Sunoco   Westville     145.0  Idling all Eagle Point refin-              Mid-Nov 
         NJ                   ing operations indefinitely due 
                              to poor economics, Co. said 
                              Oct. 6. 
 
                              Reformer unit shut in Girard      n/a 
                              Point section in early Oct 
                              for economic reasons. Shutdown 
                              to last 1-6 months. 
 
Valero   Delaware      210.0  Plant to be permanently shut due 
         City, DE             to poor economics, announced 
                              Nov. 20. Delaware Official said 
                              it would be shut on Nov. 22. 
                              The plant's production units will 
                              be dismantled and disposed of in 
                              coming months, Co. said Dec. 23. 
 
Western  Yorktown       64.5  Planned work scheduled 3Q 2010.   Q3 2010 
         VA 
 
GULF COAST 
 
Chevron  Pascagoula  330.0    Pre-commercial heavy oil          2010 
         Miss.                conversion project delayed 
                              from 2008 to 2010 due to 
                              economic factors. 
 
Flint    Corpus       288.1   $250 mln project for new          Spring 
Hills    Christi, TX          diesel desulfurization,           2010 
                              sulfur recovery unit to begin 
                              in Fall 2008. Construction 
                              to last 18 months. 
 
Marathon Garyville    245.0   Project to increase crude oil     Q2 
         LA                   refining capacity by 180,000-     2010 
                              b/d completed on schedule and 
                              new units were being integrated, 
                              company said Jan. 8. Entire 
                              plant to reach full capacity 
                              2Q, 2010, the Co. said Feb 1. 
 
                              Planned turnaround at plant       End 
                              is expected to start in Jan       Q1 
                              2010 and end late in Q1.          2010 
 
Marathon Texas City    76.0   Turnaround completed Feb. 3, 
         TX                   restarting Feb. 4-19. Entire 
                              plant shut Jan. 4; work at FCCU, 
                              SRU, alkylation units. 
 
Motiva   Convent, LA   235.0  Planned turnaround maintenance    Early 
                              began Jan 28 at several un-       April 
                              specified process units. Re- 
                              start seen in early April. 
 
Motiva   Port Arthur   285.0  Expansion project to increase     1Q 
         TX                   throughput capacity by 325,000    2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Citgo    Corpus        163.0  East Plant FCCU being restarted 
         Christi,TX           Feb. 3-5; initial start-up 
                              notifications on Dec. 28 and 
                              Jan. 7. 
 
Shell    Deer Park     340.0  Several process unit begin        Feb 17 
         TX                   restart on Jan 31 following 
                              work that began on Jan 4. 
                              Those include a hydroprocessing 
 
 
                              unit, coker, catalytic reformer, 
                              platformer, gas oil hydrotreater. 
 
Valero   Corpus       340.0   Brief unplanned maintenance to 
         Christi, TX          repair leak in Complex 3 at the 
                              West Plant on Feb 3 has no mat- 
                              erial impact to production, the 
                              Co. said. 
 
                              Coker unit returned to service    Jan 
                              in Jan 2010, the Co. said on      2010 
                              Feb 2. The 20,000-b/d unit was 
                              shut in June 2009 for economic 
                              reasons and for planned mainte-nance. 
                              nance. 
 
                              20,000-b/d FCCU in East           n/a 
                              Plant shut; West Plant 
                              50,000-b/d FCCU at reduced 
                              rates since mid-Dec for 
                              economic reasons. 
 
                              Work completed Feb 2 at the       Feb 2 
                              15,000-b/d East Plant HCU, the 
                              Co. said on Feb 2. The unit was 
                              shut for 18 days of work, the 
                              Co. said on Jan 12. 
 
                              36,000-b/d HCU in West Plant      March 
                              set for 18 days of work in Mar; 
                              delayed from Feb, the Co. said 
                              on Jan 27. 
 
Valero   Norco, LA    250.0   Crude and coker unit turnaround   March 
                              began Feb 1. Entire plant will 
                              be shut for 30 days. 
 
                              Upgrade project to build 2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur  325.0   44-days of work starts at         late Feb. 
         Tx                   FCCU, co. said Jan. 10 
 
                              77,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
                              45,000 b/d HCU to undergo         Spring 
                              38 days of work in March. 
 
Valero   Sunray, TX   170.0   55,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
Western  El Paso, TX   29.5   Planned work at south side of 
                              plant, including crude unit 
                              and FCCU in Jan for 20 days. 
 
MIDWEST 
 
BP       Toledo, OH   155.0   $400 million upgrade              2012 
                              to start 2010. 
 
Valero   Memphis, TN  195.0   105K-B/D Crude unit, FCCU         April 
                              and alkylation unit will 
                              shut in March for 45 days 
                              planned maintenance, the co. 
                              said on Jan 27. 
 
 
ROCKY MOUNTAIN 
 
Western  Bloomfield,   16.8   Co. announced plans Nov. 9 
         NM                   to idle plant and shift 
                              production to Gallup plant. 
 
Suncor   Commerce      93.0   No. 2 Crude unit will shut for    Mar 3 
         City, CO             planned maintenance on Feb 28; 
                              restart on Mar 3. 
                              No. 1 Crude unit will shut for    Mar 22 
                              planned maintenance on Mar 6; 
                              restart Mar 22. 
                              Cryo Unit will shut for planned   Apr 4 
                              maintnenance Mar 20; restart 
                              April 4. 
                              Planned work at reformer unit     Fall 
                              deferred to Fall 2010 from Feb    2010 
                              28 start date. 
 
Tesoro   Salt Lake     58.0   Major turnaround work will 
         City, Utah           begin in 1Q 2010, the Co. said 
                              on Feb 3. 
 
Tesoro   Mandan, N.D.  60.0   Planned turnaround will           2Q 
                              begin 2Q 2010, the Co. said 
                              on Feb 3. 
 
WEST COAST 
 
BP       Carson, CA   265.0   Filings to state environmen-      Feb 5 
                              tal regulators about planned 
                              flaring are seen as indicators 
                              of the end of planned mainte- 
                              nanace. A crude and a coker unit 
                              shut for planned seasonal work, 
                              source said Jan 6. Flaring will 
                              continue through Feb 5. 
 
Tesoro   Golden Eagle 166.0   Turnaround work began in early    n/a 
         Martinez,            Dec at FCCU and alkylation 
         CA                   unit, the Co. said on Feb 3. 
                              Restart timing unclear. 
                              Other major turnaround mainte-    2011 
                              nance deferred to 2011 from 
                              late 2009, the Co. said Feb 3. 
 
Tesoro   Oahu, HI      94.0   Planned turnaround work will 
         Kapolei              begin 3Q, 2010, the Co. said 
                              on Feb 3. 
 

Order free Annual Report for Alon USA Energy

Visit http://djnewswires.ar.wilink.com/?link=ALJ or call 1-888-301-0513

Order free Annual Report for BP plc

Visit http://djnewswires.ar.wilink.com/?link=BP or call 1-888-301-0513

Order free Annual Report for ConocoPhillips

Visit http://djnewswires.ar.wilink.com/?link=COP or call 1-888-301-0513

Order free Annual Report for Chevron Corporation

Visit http://djnewswires.ar.wilink.com/?link=CVX or call 1-888-301-0513

Order free Annual Report for Marathon Oil Corporation

Visit http://djnewswires.ar.wilink.com/?link=MRO or call 1-888-301-0513

Order free Annual Report for Exxon Mobil Corporation

Visit http://djnewswires.ar.wilink.com/?link=XOM or call 1-888-301-0513

 
 
Solaris Oilfield Infrast... (NYSE:SOI)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Solaris Oilfield Infrast... Charts.
Solaris Oilfield Infrast... (NYSE:SOI)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Solaris Oilfield Infrast... Charts.