The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

The fire at Exxon Mobil Corp.'s (XOM) Baton Rouge, La., refinery Wednesday morning was brief and located at a gas compressor, a company spokesman said Thursday. Of the three injured workers, two contractors were released while an employee continued to be treated at a local hospital. Exxon reaffirmed that general operations were not affected.

Exxon's refinery in Torrance, Calif., reported Wednesday that planned flaring activity that would take place April 18-30, but did not disclose details. Refineries typically submit such notices to regulators when maintenance is being conducted at units.

Valero Energy Corp. (VLO) said Thursday that the fluid catalytic cracking unit at its Quebec City refinery has returned to planned rates after repairs were completed on damage caused by an early February fire. The company's Corpus Christi refinery reported the startup of equipment following maintenance in Complex 1 and 3 at the West Plant Thursday.

Tesoro Corp. (TSO) said a sixth worker died Tuesday morning after suffering critical injuries from the Anacortes, Wash., refinery fire on April 2. A seventh worker remains in serious condition at a Seattle hospital.

BP PLC (BP) expected to begin maintenance at Pipestill 3A's Merox unit at its Texas City, Texas, refinery Wednesday evening, according to state environmental regulatory filing Tuesday. Pipestill is another name for the crude distillation unit.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
 
Operator   Refinery    Capacity   Description                     Restart 
                       (in 000s 
                       bbl/day) 
 
UNPLANNED 
 
CANADA 
 
KNOC     Newfoundland  115.0   Refinery to return to normal       end-March 
                               by end March. The entire plant 
                               was idled early Jan. to advance 
                               maintenance while repairs were 
                               made at a hydrotreater damaged 
                               by fire on Jan. 7. 
 
Valero   Quebec City   235.0   66,000-b/d FCCU shut by early- 
         Quebec                day fire on Feb 2 returned to 
                               normal rates, Co. said April 15. 
                               It was restarted over the weekend. 
                               Production was impacted by 
                               outage  but no major supply 
                               disruptions occurred due to ample 
                               inventories, Co. said. 
                               Damage assessment was delayed 
                               due to cold weather, ice on unit. 
 
 
CARIBBEAN 
 
EAST COAST 
 
GULF COAST 
 
Exxon   Baton Rouge    503.0  Three workers injured in a fire 
        La.                   on April 14. Fire was "brief" and 
                              occurred at a gas compressor, but 
                              general operations were not affected, 
                              Co. said April 15. 
 
Motiva   Norco, La.    236.4  Crude unit, DU-5, shut by fire    End 
                              on Jan 22 seen restarting in      March 
                              end-March, the Co. said on 
                              March 19. 
 
Motiva   Port Arthur   285.0  Restarted delayed coking unit 
         TX                   on April 11 after experiencing a 
                              wet gas compressor trip, a filing 
                              stated. 
 
Valero   Corpus        340.0  Unplanned maintenance at West     March 30 
         Christi, TX          Plant Complex 1 on March 28-30; 
                              SMR Unit 13 cited as emissions 
                              source in regulatory filing. 
 
BP      Texas City    455.8   Cat feed hydrotreating unit had 
        TX                    a process upset April 9. 
 
MIDWEST 
 
ROCKY MOUNTAINS 
 
WEST COAST 
 
Chevron   El Segundo   279.0  Isomax plant shut March 19        n/a 
          CA                  due to "small" fire. No 
                              estimate on restart. 
 
Chevron   Richmond     245.3  Refinery lost compressor 
          CA                  causing flaring April 7. 
 
 
Tesoro    Wilmington   100.0  Hydrocracker Unit Shut April 5. 
 
Tesoro    Anacortes    120.0  Fire at naptha unit April 2 
          WA                  killed six; one worker remains 
                              in serious condition, company 
                              said April 13. 
 
                              All production operations to 
                              temporarily shut down later this 
                              month until repair are done and 
                              investigations progress, company said 
                              April 12. Supply will be met from 
                              other companies' refineries or from 
                              spot market. Plant was processing 
                              70,000 b/d if crude after blast. 
 
PLANNED 
 
CANADA 
 
Shell    Montreal     130.0   The refinery will be converted 
         Quebec               into a fuel terminal, Co. said 
                              Jan. 7. No timeline provided. 
 
 
CARIBBEAN 
 
Valero   Aruba        235.0   The plant, which 
                              was shut in June for 2-3 
                              months for economic reasons was 
                              closed indefinitely in Nov. 
 
EAST COAST 
 
Hess     Port                 Month-long turnaround work 
         Reading NJ           will take place in April at 
                              the plant's 70,000-b/d 
                              FCCU; the refinery does not 
                              process crude oil. 
 
Sunoco   Westville     145.0  Idling all Eagle Point refin-     n/a 
         NJ             ing operations indefinitely due 
                              to poor economics, Co. said 
                              Oct. 6. 
 
                              Reformer unit shut in Girard      n/a 
                              Point section in early Oct 
                              for economic reasons. Shutdown 
                              to last 1-6 months. 
 
Valero   Delaware      210.0  PBF Investments has reached deal            April 2012 
                              to buy plant. Could be fully operational 
                              by April 2012. 
 
Western  Yorktown       64.5  Planned work scheduled 3Q 2010.   Q3 2010 
         VA 
 
 
GULF COAST 
 
Alon     Krotz         100.0  Refinery will restart in 
         Springs, La.         April. 
 
BP      Texas City     455.8  Ultraformer No. 4 restarted       March 23 
        TX                    March 23 after shutting down 
                              for repairs on March 19. Emis- 
                              sions are expected to last 
                              until March 27. 
 
                              Planned maintenance related to 
                              April 6 "J457 compressor" April 1-6. 
                              Train 400 at resid hydrotreater 
                              being restarted April 12 after 
                              maintenance activity. 
 
                              Maintenance on Pipestill 3A's    April 17 
                              Merox unit began April 14 and 
                              to conclude April 17. Pipestill 
                              is another name for a crude 
                              distillation unit. 
 
 
Chevron  Pascagoula  330.0    Pre-commercial heavy oil          2010 
         Miss.                conversion project delayed 
                              from 2008 to 2010 due to 
                              economic factors. 
 
                              Work is progressing on the 
                              continuous catalytic reformer, 
                              expected to be completed by 
                              mid-2010, Co. said Feb. 25. 
                              Co. is planning to put a premium 
                              base-oil facility at plant. 
 
Conoco   Borger     146.0     Shuts FCCU April 7 for repairs    April 14 
           Tx 
 
Conoco    Sweeny     247.0    Shuts unnamed unit for work,       n/a 
           Tx                 April 8. 
 
Flint    Corpus               $250 mln project for new Spring   2010 
Hills    Christi, TX          diesel desulfurization, 
                              sulfur recovery unit to begin 
                              in Fall 2008. Construction 
                              to last 18 months. 
 
Marathon Garyville    436.0   Plant operating at newly ex-      n/a 
         LA                   panded capacity and may ex- 
                              ceed it, the co. said on March 
                              25. 
 
Motiva   Convent, LA   235.0  Planned turnaround maintenance    Early 
                              began Jan 28 at several un-       April 
                              specified process units. Re- 
                              start seen in early April. 
 
Motiva   Port Arthur   285.0  Expansion project to increase     1Q 
         TX                   throughput capacity by 325,000    2012 
                              b/d, to 610,000-b/d, slowed. 
                              Completion now seen 1Q 
                              2012, from 2010. 
 
Valero   Corpus       340.0   Plant shut; West Plant            n/a 
         Christi, TX          50,000-b/d FCCU at reduced 
 
 
                              rates since mid-Dec for 
                              economic reasons. 
 
                              36,000-b/d HCU in West Plant      March 
                              restarted, Co. said March 16, 
                              after about 18 days of work 
                              delayed from Feb. 
 
                              Planned work on SMR unit began 
                              at West Plant on April 12. 
                              Reported restart of equipment 
                              after maintenance at West Plant's 
                              Complex 1 and 3 on April 15. 
 
Valero   Norco, LA    250.0   Upgrade project to build 2012 
                              a new diesel hydrotreater 
                              unit moved from 2010 to 
                              4Q 2012. 
 
Valero   Port Arthur  325.0   Hydrocracker turnaround lasting 
                              38 days has begun, Co. said 
                              March 15. 
 
                              77,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
Valero   Sunray, TX   170.0   55,000-b/d FCCU at reduced        n/a 
                              rates since mid-Dec for 
                              economic reasons. 
 
Valero   Texas City   245.0   Repaired an exchanger leak 
         TX                   found in the alkylation unit 
                              located at Complex 2, Co. 
                              said March 15. 
 
Marathon Texas City    76.0   FCCU being restaretd March 31 
         TX                   after completing required 
                              maintenance. 
 
MIDWEST 
 
BP       Toledo, OH   155.0   $400 million upgrade              2012 
                              to start 2010. 
 
Valero   Memphis, TN  195.0   Crude unit restarted, while        end- 
                              overhaul of FCCU and alky-        April 
                              lation unit continues, the 
                              company said March 26. 
                              The entire plant had been 
                              off-line since March 14. 
 
Marathon Catlettsburg 226.0   Turnaround maintenance at un-     n/a 
         KY                   specified units starts March 
                              10. No restart estimate. 
ROCKY MOUNTAIN 
 
Western  Bloomfield,   16.8   Co. announced plans Nov. 9 
         NM                   to idle plant and shift 
                              production to Gallup plant. 
 
Suncor   Commerce      93.0   No. 1 Crude unit will shut for    Mar 22 
         City, CO             planned maintenance on Mar 6; 
                              restart Mar 22. 
                              Cryo Unit will shut for planned   Apr 4 
                              maintnenance Mar 20; restart 
                              April 4. 
                              Planned work at reformer unit     Fall 
                              deferred to Fall 2010 from Feb    2010 
                              28 start date. 
 
Tesoro   Salt Lake     58.0   Major turnaround work will 
         City, Utah           begin in 1Q 2010, the Co. said 
                              on Feb 3. 
 
Tesoro   Mandan, N.D.  60.0   Planned turnaround will           2Q 
                              begin 2Q 2010, the Co. said 
                              on Feb 3. 
 
WEST COAST 
 
Exxon    Torrance, CA 150.0   FCCU, alkylation unit shut        Apr 10 
                              March 20-21 as part of turn- 
                              around maintenance that be- 
                              gan March 1 at several units. 
                              The work is expected to last 
                              for 40 days, trade sources said 
                              on Feb. 11. 
 
                              Planned flaring activity to take 
                              place April 18-30, but no details 
                              of cause provided in April 14 
                              filing. 
 
BP      Carson, CA    265.0   Planned flaring activity  on 
                              March 29-April 20 and, Co. reported 
                              in filings. 
 
                              Planned flaring activity reported 
                              for April 4-9, an April 1 filing said. 
 
                              Planned flaring for April 14-20, Co. 
                              reported April 13. 
 
 
Tesoro   Golden Eagle 166.0   Turnaround work began in early    n/a 
         Martinez,            Dec at FCCU and alkylation 
         CA                   unit, the Co. said on Feb 3. 
                              Restart timing unclear. 
                              Other major turnaround mainte-    2011 
                              nance deferred to 2011 from 
                              late 2009, the Co. said Feb 3. 
 
 
Tesoro   Oahu, HI      94.0   Planned turnaround work will 
         Kapolei              begin 3Q, 2010, the Co. said 
                              on Feb 3. 
 
                              Planned work deferred to 2011 from 
                              late 2009, the Co. said Feb 3. 
 
Chevron  El Segundo   279.0   Reported flaring and cause was being 
         CA                   investigated, an April 9 filing said. 
 

Order free Annual Report for BP plc

Visit http://djnewswires.ar.wilink.com/?link=BP or call 1-888-301-0513

Order free Annual Report for ConocoPhillips

Visit http://djnewswires.ar.wilink.com/?link=COP or call 1-888-301-0513

Order free Annual Report for Hess Corporation

Visit http://djnewswires.ar.wilink.com/?link=HES or call 1-888-301-0513

Order free Annual Report for Holly Corp.

Visit http://djnewswires.ar.wilink.com/?link=HOC or call 1-888-301-0513

Order free Annual Report for Marathon Oil Corporation

Visit http://djnewswires.ar.wilink.com/?link=MRO or call 1-888-301-0513

Order free Annual Report for Suncor Energy Inc.

Visit http://djnewswires.ar.wilink.com/?link=SU or call 1-888-301-0513

Order free Annual Report for Tesoro Corporation

Visit http://djnewswires.ar.wilink.com/?link=TSO or call 1-888-301-0513

Order free Annual Report for Exxon Mobil Corporation

Visit http://djnewswires.ar.wilink.com/?link=XOM or call 1-888-301-0513

 
 
Harvest Energy (NYSE:HTE)
Historical Stock Chart
From Oct 2024 to Nov 2024 Click Here for more Harvest Energy Charts.
Harvest Energy (NYSE:HTE)
Historical Stock Chart
From Nov 2023 to Nov 2024 Click Here for more Harvest Energy Charts.