TIDMBZM
RNS Number : 6100I
Bellzone Mining PLC
17 June 2011
17 June 2011
Bellzone Mining plc
("Bellzone" or the "Company")
Forecariah JV Progress Update
-- Project on schedule to achieve production Q1 2012
-- Diamond and Reverse Circulation drilling progressing
-- Phase I internal resource (tonnage) estimates expected July
2011 and internal resource classification Q3 2011
-- Port studies for completion in July 2011
-- Construction of road to port site commenced
-- Mine developments on schedule
-- First phase of mine camp constructed
Bellzone Mining plc (AIM:BZM) is pleased to report that the
Forecariah JV Project (the "JV") with China International Fund
("CIF") in the Republic of Guinea, West Africa, is on schedule to
commence production of iron ore in Q1 of 2012.
Resource Development
In December 2010, the Company commissioned an independent
geologist to undertake a review of previous work done on the area
and to design a resource development plan. A number of targets
(Yomboyeli, Layah, Moussayah, Santiguiyah and Doto) were identified
and Yomboyeli was selected for initial development.
The Phase I resource development, includes mapping, surface
sampling and drilling. Bellzone expects to be announcing Phase I
internal resource estimates in July with an internal resource
classification expected in Q3 2011. Work done on the Phase I
resource to date includes:
-- 16 diamond drill ("DD") holes totalling 1,600 metres up to a
depth of 112 metres have been drilled to delineate the oxide
structure
-- All drill holes have intersected iron ore mineralisation
-- 1,880 metres in 21 trenches have been completed to map and
identify the surface oxide
-- 2.7km(2) area showing oxide at surface has been mapped
-- Phase 1 of the resource development programme, utilising
reverse circulation ("RC") drilling, will focus on 0.7km(2) of the
initial 2.7km(2) is in progress
-- 15 of the 112 hole Phase I RC drilling programme have been
completed delivering 1,510 metres
-- Phase II of the RC drilling programme will infill the Phase I
drilling profiles and consists of 117 drill holes.
-- Trench, DD and RC samples will be flown to laboratories in
China and Australia for analysis
-- Three additional diamond drill rigs have been purchased and
are due on site in July 2011 to increase the rate of
development.
All drill holes have intersected oxide showing a surface oxide
iron layer of between 8 and 33 metres with iron enriched schist at
depths of up to 112 metres. In addition, mapping and drilling to
date has shown multiple parallel oxide zones extending to the depth
of drilling across the mapped 2.7km(2) initial target area. Phase
III resource development will focus on the remainder of the
2.7km(2) initial target with results expected in late Q4 2011.
Road Development
The road route from Yomboyeli to the port site has been
surveyed. The 76km route comprises 20km of new road required to
bypass villages, and 56 km of existing road. The existing road
upgrade and new road construction to support the bulk ore road
trains will be done in four sections.
Approval has been granted to start construction on the section
of road from Konta (port location) to the Woulla village (section
1) near the tarred main road, approximately 22 km. Bellzone has
contracted Entreprise Generale des Travaux et Transports ("EGTT")
and the work has commenced. The scope of work includes:
-- Road widening to support road trains
-- Road base upgrades
-- Culvert construction and upgrades
-- Road signage
The route optimisation and environmental impact assessment on
the two sections between Woulla village and Moussayah are due for
completion in July 2011.
The request for approval to start construction on section 4
between Yomboyeli / Moussayah, approximately 33 km, has been
submitted to the Government and approval is expected within the
next few weeks after which construction will begin.
Tender packages have been issued to contractors and awarding of
the tenders is scheduled for July 2011.
Konta Port Development
The survey, study and engineering design contract was awarded to
China Communication Construction Company's ("CCCC") Second Harbour
Consultants Co. in January 2011 for the stockyard and barge loading
facilities at Konta. CCCC have completed the following work:
-- 73 holes drilled to assess marine and land geotechnical
conditions
-- Marine and land based topographic mapping complete
-- Tides, climate and water flow assessments (in progress, due
for completion shortly)
-- Stockyard and barge loading layouts
-- Preliminary cost estimates.
The CCCC will complete the stockyard and barge loading
feasibility study which is scheduled for completion in July
2011.
Site acquisition and clearance is expected to commence in August
2011 on completion of the socio-economic and environmental impact
assessment studies which are in progress.
Mine and Plant Development
The Bellzone and CIF mining team has completed:
-- Preliminary mine and plant production solutions. Mobile
crushing and screening plants are planned to produce two iron ore
products (lump and fine) and tenders have been prepared for issue
to potential suppliers.
-- Preliminary mining fleet selected based on assumed mining
requirements and initial resource data. Tenders have been prepared
for issue to potential suppliers.
Key assumptions will be reviewed on completion of the Phase I
resource classification which is expected in Q3 2011 and
preliminary mine construction is expected to commence in July 2011
with environmental approval expected in Q3 2011.
Support infrastructure
The project support infrastructure has progressed significantly
over the past two months. In addition to the establishment of a
joint office in Beijing with CIF that will also accommodate Kalia
related studies, the JV has established:
-- An office for the JV operating company, Forecariah Guinea
Mining, in Conakry and located in same building as CIF and
Bellzone
-- A 45 person camp at Yomboyeli to facilitate the resource
development and early works
-- A core shed for geological logging and assessment of drill
core and samples.
Nik Zuks, Chief Executive Officer, commented: "These are
exciting times. I am very pleased with the progress achieved in a
short time by our combined CIF and Bellzone team and with the
strong support received from the Guinea government for both our
major projects. The JV is working very well, project management is
strong and everyone associated with the project is focussed on
achieving production in Q1 2012. "
The mineral resource information disclosed in this announcement
has been reviewed by Peter Batten, BAppSc, member of the
Australasian Institute Mining and Metallurgy. He has sufficient
experience relevant to the style of mineralisation and type of
deposit under consideration and to the activity which is being
undertaken, to qualify as a Competent Person for the purposes of
this announcement.
Enquiries:
Bellzone Mining plc
Nik Zuks/Graham Fyfe +61 (0) 8 9420 8900
Canaccord Genuity Limited
Nominated Adviser and Joint Broker
to Bellzone +44 (0)20 7050 6500
Andrew Chubb/Tarica Mpinga
Renaissance Capital Limited
Joint Broker to Bellzone +44 (0)20 7367 7777
Simon Matthews
Tavistock (UK)
Jos Simson/Paul Youens +44 (0)20 7 9203 150 / +44 (0)7899
870 450
PPR (Australia)
David Ikin +61 (0) 8 9388 0944 / +61 (0)
408 438 772
Bellzone Mining Plc
Bellzone Mining plc is an exploration and resource development
company with iron ore and nickel / copper permits in the Republic
of Guinea, West Africa.
Kalia Mine
The Company's flagship project, the Kalia Mine, has a magnetite
JORC resource of 3.74 billion tonnes, located on the Kalia I
prospect and an initial oxide JORC resource producing 43 million
tonnes of 58% product from just 4.3% of the 55km(2) of the mapped
surface oxides on the Kalia permit. Drilling results and internal
estimates indicate that the Kalia Prospect has the potential to
host more than 10 billion tonnes of magnetite and 2 billion tonnes
of oxide.
Bellzone plans to develop the Kalia Mine in two stages;
-- commencing with a 20mtpa oxide production facility in 2014
and a 10mtpa magnetite concentrator in 2015,
-- stage two increases oxide output to 30mtpa in 2017 and
doubles the concentrate output to 20mtpa in 2018.
CIF - Project, Financing & Infrastructure Partner
Bellzone has a Definitive Agreement ("the Agreement") with China
International Fund Limited ("CIF"). The Agreement gives CIF right
of first refusal to purchase Kalia' s production at market rates
and CIF commits to providing Bellzone commercially related funding
for the development of the Kalia Mine Project.
The Agreement contains CIF's commitment to fund and build a
commercially operated rail and port infrastructure that will enable
Bellzone to export production from Kalia. The infrastructure is
being developed by Kalia Horizon Minerals Pte Limited that is 90%
owned by CIF with Bellzone having a 10% carried interest. The
Agreement provides for Bellzone to be the lowest cost user with
permanent priority access.
Forecariah JV
In addition to the Kalia Mine Project, Bellzone and CIF have
fully funded a joint venture to undertake the accelerated
exploration and development programme at CIF's Forecariah iron
permits that lie between 30 and 80 kms from the Guinea coast.
Production will start in Q1 2012 and will target an initial
production rate of 3-4 mtpa of oxide ore ramping to a rate of 10
mtpa in 2013.
This information is provided by RNS
The company news service from the London Stock Exchange
END
DRLEAXKKFEXFEFF
Bellzone Mining (LSE:BZM)
Historical Stock Chart
From Jun 2024 to Jul 2024
Bellzone Mining (LSE:BZM)
Historical Stock Chart
From Jul 2023 to Jul 2024