TIDMOSU 
 
Orsu Announces Positive Results of a Scoping Study for the Tadybulak Gold-Copper-Molybdenum Porphyry Deposit in Kyrgyzstan 
FOR:  ORSU METALS CORPORATION 
 
TSX, AIM SYMBOL:  OSU 
 
November 11, 2010 
 
Orsu Announces Positive Results of a Scoping Study for the Tadybulak Gold-Copper-Molybdenum Porphyry Deposit in 
Kyrgyzstan 
 
- Average annual production of more than 240,000 oz gold, 26,000 t copper and 900 t molybdenum; 
 
- US$516 million initial CAPEX; 
 
- US$815 million pre-tax NPV 7.5; 
 
- 24.7% pre-tax IRR (using US$1,150/oz Au, US$3.00/lb Cu, US$15/lb Mo); 
 
- 17 years Life of Mine 
 
- 6 Years Payback from start of construction 
 
LONDON, UNITED KINGDOM--(Marketwire - Nov. 11, 2010) - Orsu Metals Corporation ("Orsu", or the "Company") 
(TSX:OSU)(AIM:OSU), the London-based precious and base metals exploration and development company, is pleased to 
announce the positive results of a scoping study for the Tadybulak Gold-Copper-Molybdenum Porphyry Deposit 
("Taldybulak") at its Talas joint venture project in the Kyrgyz Republic (the "Taldybulak Scoping Study"). Gold Fields 
Limited ("Gold Fields"), through its subsidiary Gold Fields Orogen Holding BVI Limited, has a 60% interest in the Talas 
joint venture company (the indirect owner of the Taldybulak, Barkol, Kentash and Korgontash licenses in the Talas region 
of the Kyrgyz Republic (the "Talas Project")), whilst Orsu retains a 40% interest in the Talas Project. Gold Fields is 
the project manager. 
 
The Taldybulak Scoping Study establishes key design criteria for an open pit mine scenario with a 15 million tonnes per 
annum ("Mtpa") processing facility for average annual recovery of 242,000 oz gold and 137,600 dry metric tonnes ("dmt") 
of copper concentrate and 1,880 dmt of molybdenum concentrate via conventional communition and floatation process flow 
sheets at estimated initial capital expenditures of approximately US$516 million. 
 
Taldybulak has been the primary focus of exploration and mineral resource development within the Talas Project licence 
area. The Talas Project is located 250 km west of the Kyrgyz capital of Bishkek and is accessible all year via paved 
road up to the last 20 km. The national electrical grid is close to the deposit and there is a 110kV sub-station 20km 
from the site. There is a potential water source for future operations from ground water aquifers and from the Karakol 
river. The average project elevation is approximately 2,000 m and the nearest village with a population of 3,500 people 
is 7 km away. The larger town of Talas with 30,000 people is approximately 50 km to the west. The nearest railhead is at 
Maimak on the Kazakhstan border, approximately 160 km away via paved road. 
 
Coffey Mining Pty Ltd (Perth, Australia) ("Coffey Mining") completed the Taldybulak Scoping Study on behalf of the Talas 
joint venture, which formed a basis for a pit-constrained mineral resource update for the deposit. This was done 
according to the 2007 South African Code for the Reporting of Mineral Resources and Mineral Reserves (the "SAMREC Code 
Resource"). The SAMREC Code Resource contains 127 Mt in the indicated category, which is comprised of 2.6 Moz gold at 
0.64 g/t, 477 Mlb copper at 0.17%, and 29.4 Mlb molybdenum at 0.01%, and 296 Mt in the inferred category, which is 
comprised of 3.71 Moz gold at 0.40 g/t, 1,098 Mlb copper at 0.17%, and 69.2 Mlb molybdenum at 0.01%. The mineral 
resource was calculated using metal prices of US$1,150/oz Au, US$3.00/lb Cu, US$15/lb Mo ("Resource Price Case"), which 
was reported in the Company's press release dated September 27, 2010. 
 
Preliminary metallurgical test work (as reported by Orsu in its press-release dated July 21, 2010) indicated that the 
recovery of gold, copper and molybdenum should be possible using a conventional communition and flotation process. Based 
on metallurgical test work results, a conceptual process flow sheet has been developed consisting of crushing, grinding 
and bulk flotation to produce a gold-copper-molybdenum concentrate. The concentrate would then undergo a further 
flotation stage to produce both a copper-gold concentrate and a molybdenum concentrate. In this scenario some copper 
must be present in order to recover any other elements, therefore any Standard Mining Unit ("SMU") containing some gold 
but zero copper would not be profitable to treat. Due to the polymetallic nature of the Taldybulak ores, material that 
is profitable to treat is not simply based on a single element cut-off grade. Figure 1 shows which material is 
potentially economic at various copper and gold grades for a maximum cashflow scenario using the Resource Price Case, 
i.e., US$1,150/oz gold, US$3.00/lb copper, and US$15/lb molybdenum metal prices. Due to the minor contribution from 
molybdenum, an average molybdenum grade of 0.011% molybdenum is assumed. The copper grade that is economic to treat 
excluding gold credits is approximately 0.16% Cu. 
 
To view Figure 1. Taldybulak economic cutoff grades based on molybdenum grade of 0.011% and metal prices of US$1,150/oz 
gold, US$3.00/lb copper and US$15.00 molybdenum, please visit the following link: 
http://media3.marketwire.com/docs/osu_11_11_2010_fig_1.pdf 
 
In addition to production of copper and molybdenum concentrates, gravity gold recovery is 15%, which warrants a gravity 
separation circuit prior to bulk flotation for any coarse gold that may be present to produce Dore bars on site. 
Evaluation of the potential to treat oxide material from the deposit is being investigated, however at this time no 
value has been attributed to the oxides. Transition material has been incorporated into the mining schedule with reduced 
recoveries based on testwork conducted in 2008. 
 
Both indicated and inferred mineral resources have been used for mining and processing optimisation in the Taldybulak 
Scoping Study; no mineral reserves have been estimated or reported for Taldybulak. An open pit mining scenario based on 
20mEastx20mNorthx10m vertical SMU with a processing rate of 15 Mtpa of ore has been assumed. 
 
Mining and processing parameters and long term commodity price assumptions ("Base Price Case") were used to select a 
maximum discounted (7.5%) cash flow open pit shell. Key design criteria have been established for a 15 Mtpa processing 
plant facility (Table 1). The key design criteria assumptions and proposed metallurgical performance are generally based 
on the processing of sulphide ore, except where transition ore characteristics are known. 
 
Table 1. Key Design Criteria Summary 
 
 
 
=-------------------------------------------------------------------------- 
Parameter                                               Unit       Criteria 
=-------------------------------------------------------------------------- 
Annual throughput                                       Mtpa           15.0 
=-------------------------------------------------------------------------- 
Crushing plant availability                                %             70 
=-------------------------------------------------------------------------- 
                                                 hrs/day and 
Crushing plant operation                           days/week       17 and 7 
=-------------------------------------------------------------------------- 
Processing plant availability                              %             92 
=-------------------------------------------------------------------------- 
                                                 hrs/day and 
Processing plant operation                         days/week       24 and 7 
=-------------------------------------------------------------------------- 
                                                       micro 
P80 grind size                                        metres             75 
=-------------------------------------------------------------------------- 
                                                      g/t Au           0.60 
Ore feed grade                                          % Cu           0.20 
                                                        % Mo           0.01 
=-------------------------------------------------------------------------- 
                                                     % Au(i)           81.4 
Metal recovery                                          % Cu           88.0 
                                                        % Mo           53.2 
=-------------------------------------------------------------------------- 
Gravity gold recovery                                   % Au             15 
                                        ----------------------------------- 
Annual concentrate production             dmt Cu concentrate        137,600 
                                          dmt Mo concentrate          1,880 
                                        ----------------------------------- 
Annual gold production                                 oz Au        242,000 
=-------------------------------------------------------------------------- 
Table notes: 
(i) Inclusive of gravity gold recovery. 
This table represents design criteria for the process design work. Actual 
figures for metallurgical recovery will depend on head grade. 
=-------------------------------------------------------------------------- 
 
 
 
Analysis of the topography demonstrated that there is enough space to build tailings storage facilities ("TSF") in the 
immediate vicinity of Taldybulak. However, a detailed TSF engineering study has not been undertaken. Work to better 
define the TSF design is ongoing. 
 
Although the actual pit-constrained mineral resource is 127Mt of ore in the indicated category and 296 Mt of ore in the 
inferred category using US$1,150/oz, US$3.00/lb Cu and US$15/lb Mo, the Taldybulak Scoping Study is based on a re- 
modelling of the open pit using the Base Price Case of US$1,000/oz Au, US$2.49/lb Cu, and US$15/lb Mo. The total 
combined resource used for the Taldybulak Scoping Study was 254 Mt of ore (indicated and inferred) using the Base Price 
Case. 
 
Table 2 shows a price sensitivity analysis of four alternative metal price scenarios for open-pit mining at Taldybulak, 
using 254 Mt of ore in both indicated and inferred resource categories, optimised to an open pit defined by the Base 
Price Case. Consequently, the change in metal prices incorporated in the sensitivity to the cash flow does not fully 
reflect the impact the change in metal prices would have on the project as the optimised pit shell and cut-off grade 
were not adjusted. Preliminary indications are that the project economics would be enhanced with a larger pit and lower 
cut-off grade; however, this was a high-level evaluation and plant throughput, tailings storage, capital cost and unit 
operating costs were not optimised and updated to account for the increase in tonnage. 
 
Table 2. Sensitivity Analysis Results 
 
 
 
=-------------------------------------------------------------------------- 
                                               3-Year 
                                              Average   Resource       Spot 
                                Base Price      Price      Price      Price 
Parameter           Unit              Case     Case(i)      Case     Case(i) 
=-------------------------------------------------------------------------- 
Gold price          US$/oz           1,000        976      1,150      1,319 
=-------------------------------------------------------------------------- 
Copper price        US$/lb            2.49       2.92       3.00       3.67 
=-------------------------------------------------------------------------- 
Molybdenum price    US$/lb           15.00      20.46      15.00      14.95 
=-------------------------------------------------------------------------- 
Average annual 
 throughput         Mtpa                15         15         15         15 
=-------------------------------------------------------------------------- 
Waste : Ore Ratio                     1.29       1.29       1.29       1.29 
=-------------------------------------------------------------------------- 
Gold grade          g/t Au            0.52       0.52       0.52       0.52 
=-------------------------------------------------------------------------- 
Gold metal 
 recovered          Moz Au           3.401      3.401      3.401      3.401 
=-------------------------------------------------------------------------- 
Copper grade        %                 0.18       0.18       0.18       0.18 
=-------------------------------------------------------------------------- 
Copper metal 
 recovered          kt Cu              391        391        391        391 
=-------------------------------------------------------------------------- 
Molybdenum grade    %                0.011      0.011      0.011      0.011 
=-------------------------------------------------------------------------- 
Molybdenum metal 
 recovered          kt Mo             13.9       13.9       13.9       13.9 
=-------------------------------------------------------------------------- 
Gold grade 
 equivalent         g/t Au            0.95       1.05       0.94       0.95 
=-------------------------------------------------------------------------- 
Average annual      koz Au             242        242        242        242 
 production         kt Cu             26.2       26.2       26.2       26.2 
                    t Mo               900        900        900        900 
                    koz Au 
                     equivalent        353        389        356        361 
=-------------------------------------------------------------------------- 
LOM recoverable     Moz Au 
 ounces              equivalent       6.01       6.62       6.05       6.14 
=-------------------------------------------------------------------------- 
Average cash cost   US$/oz Au 
                     equivalent        445        404        443        436 
=-------------------------------------------------------------------------- 
Total cash costs    US$/oz Au 
                     equivalent        621        571        624        622 
=-------------------------------------------------------------------------- 
Initial Capex       US$ M              516        516        516        516 
=-------------------------------------------------------------------------- 
Ongoing Capex       US$ M            275.2      275.2      275.2      275.2 
=-------------------------------------------------------------------------- 
Years of production Years               17         17         17         17 
=-------------------------------------------------------------------------- 
0% pre-tax NPV      US$ M          1,257.7    1,647.8    2,125.8    3,181.1 
=-------------------------------------------------------------------------- 
7.5% pre-tax NPV 
 (base case)        US$ M            384.4      571.8      814.7    1,337.3 
=-------------------------------------------------------------------------- 
Pre-tax IRR         %                 16.3       20.1       24.7       34.1 
=-------------------------------------------------------------------------- 
Payback period 
 (from start of 
  2-year-long 
  construction)     Years                9          8          6          5 
=-------------------------------------------------------------------------- 
Table notes: 
The cashflow model accounts for royalties, but does not account for taxes. 
Some figures may not sum exactly due to rounding. 
(i) 3 year average price and spot price from Bloomberg Data as of 1st 
October 2010 
Gold equivalent is calculated for each case separately using commodity 
price weightings for gold, copper and molybdenum in this Table. 
'koz Au equivalent' equals 'koz Au' + ('Copper price US$/lb' x 'ktCu' x 
2,200+'Molybdenum price US$/lb' x 'tMo' x 2,200)/'Gold price US$/oz'; 
'Moz Au equivalent' equals 'Gold metal recovered Moz Au' + ('Copper price 
US$/lb' x 'Copper metal recovered ktCu' x 2,200 + 'Molybdenum price 
US$/lb' x 'Molybdenum metal recovered ktMo' x 2,200)/'Gold price 
US$/oz' 
=-------------------------------------------------------------------------- 
 
 
 
The Taldybulak Scoping Study is a preliminary estimate of the technical and economic viability of Taldybulak and does 
not contemplate the full spectrum of engineering, economic and regulatory factors, which would be required prior to 
making a production decision. Estimates provided in the Taldybulak Scoping Study are subject to change as additional 
work is completed on the project. 
 
The Taldybulak Scoping Study is preliminary in nature, and includes inferred mineral resources that are considered too 
speculative geologically to have the economic considerations applied to them that would enable them to be categorized as 
mineral reserves. There is no certainty that the Taldybulak Scoping Study will be realized. Mineral resources that are 
not mineral reserves do not have demonstrated economic viability. 
 
Dr Sergey V Kurzin, Executive Chairman of Orsu, commented: "We are very pleased with the positive results of the 
Taldybulak Scoping Study, with some parameters, such as electricity and concentrate transportation costs, estimated 
conservatively. Nevertheless, the IRR values are high for a porphyry-type deposit. The project has excellent 
infrastructure and is located in relatively gentle terrain, amenable to open pit mining with low stripping ratio. The 
Talas joint venture will continue to focus on the improvement of Taldybulak metal grades through the 5000 m closely- 
spaced infill drilling programme which is planned to start after the winter season. The joint venture will also continue 
the optimization of economic and processing parameters, particularly its oxide ores." 
 
Notes to editor: 
 
 
 
1.  Further information on the Talas Project contained in the Updated 
    Technical Report on the Taldybulak Property Held by Orsu Metals 
    Corporation, Kyrgyzstan March 2010 was filed under the Company profile 
    on SEDAR (www.sedar.com). 
2.  Mr Rodney Smith, BSc, MAusIMM, Principal Consultant - Metallurgy with 
    Coffey Mining Pty Ltd (Perth, Australia) is the person responsible for 
    the preparation of the report titled "Talas Scoping Study, Talas 
    Taldybulak Project, Kyrgyzstan, 2010" based on which this press release 
    was prepared. 
3.  Alexander Yakubchuk, PhD, Director of Exploration and Chief Operating 
    Officer for Orsu and a "qualified person" as such term is defined in 
    National Instrument 43-101 and for the purposes of the AIM Guidance Note 
    for Mining, Oil & Gas Companies, has prepared and reviewed the contents 
    of this press release. Dr Yakubchuk has verified the data disclosed in 
    this release, including sampling, analytical and test data underlying 
    the information. 
 
 
 
FORWARD-LOOKING INFORMATION 
 
This press release contains forward-looking information which is not comprised of historical facts. Forward-looking 
information involves risks, uncertainties and other factors that could cause actual events, results, performance and 
opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking 
information contained (or referred to) in this press release includes, but may not be limited to: estimated average 
annual production of gold equivalent at Taldybulak; net present value, initial rate of return and expenditures relating 
to Taldybulak; the anticipated timing of capital payback; estimated tonnage and contained gold equivalents at 
Taldybulak; future activities and operations at Taldybulak; a potential water source at Taldybulak; future recoveries 
and related processes at Taldybulak; the future production of a gold-copper-molybdenum concentrate and the methods 
relating thereto; the future price of gold, copper and molybdenum; the economic potential and grades for gold and copper 
at Taldybulak; the potential to treat oxide material at Taldybulak; mineral resource estimates; the Company's ability to 
better define the TSF design; management's expectation that project economics will be enhanced at Taldybulak by using a 
larger pit and lower cut-off grade; the estimates contained in Table 1 above; the potential for improvement of the metal 
grades at Taldybulak; and the proposed continuation of optimization of economic and processing parameters at Taldybulak. 
 
Factors that could cause actual results to differ materially from those described in such forward-looking information 
include, but are not limited to, risks normally incidental to exploration and development of mineral properties, 
uncertainties in the interpretation of drill and test results, the possibility that future exploration, development 
and/or mining results will not be consistent with expectations, uncertainty of mineral resources estimates, risks 
relating to the methodologies employed in the Taldybulak Scoping Study and that the completion of additional work on 
Taldybulak could result in changes to the estimates contained in the Taldybulak Scoping Study, the Company's inability 
to obtain, maintain, renew and/or extend required licences, permits, authorizations and/or approvals from the 
appropriate regulatory authorities, including (without limitation) extensions of the Taldybulak and Barkol licences 
after December 31, 2010, and other risks relating to the political, environmental, regulatory and/or legal framework in 
Kyrgyzstan, adverse changes in commodity prices or the Talas joint venture, as well as certain other risks set out in 
the Company's public documents, including its annual information form dated March 24, 2010, filed under the Company's 
profile on SEDAR at www.sedar.com. 
 
The forward-looking information in this press release reflects the current expectations, assumptions and/or beliefs of 
the Company based on information currently available to the Company. In connection with the forward-looking information 
contained in this press release, the Company has made assumptions about: the Company's business, the economy and the 
mineral exploration industry in general; future capital expenditures and cost parameters, including the Resource Price 
Case, Base Price Case, Spot Price Case and 3-Year Average price Case; tonnage and contained gold equivalents at 
Taldybulak; the presence of copper at Taldybulak in order to recover other elements; future commodities' prices and that 
no material adverse changes occur relating thereto; average copper and molybdenum grades; indicated and inferred mineral 
resources at Taldybulak; anticipated mining methods and processing rates; cash flow discounts; the design criteria set 
out in Table 1 above; the Company's ability to enhance project economics at Taldybulak by using a larger pit and lower 
cut-off grade; the Company's ability to raise any required additional financing, as needed; the regulatory framework in 
Kyrgyzstan with respect to, among other things, the Company's ability to obtain, maintain, renew and/or extend required 
permits, licences, authorizations and/or approvals from the appropriate regulatory authorities, including the Company's 
ability to obtain extensions of the Taldybulak and Barkol licences after December 31, 2010; the political environment in 
Kyrgyzstan; and the Company's ability to continue to obtain qualified staff and equipment in a timely and cost-efficient 
manner to meet the Company's demand. The Company has also assumed that no unusual geological or technical problems 
occur, plant and equipment work as anticipated and no significant events occur outside of the Company's normal course of 
business. Although the Company believes that the assumptions inherent in the forward-looking information are reasonable, 
forward-looking information is not a guarantee of future performance and accordingly undue reliance should not be put on 
such information due to the inherent uncertainty therein. 
 
The mineral resource figures contained and/or referred to in this press release are estimates only and no assurances can 
be given that the indicated levels of minerals will be produced. Such estimates are expressions of judgment based on 
knowledge, mining experience, analysis of drilling results and industry practices. Valid estimates made at a given time 
may significantly change when new information becomes available. While the Company believes that the mineral resource 
estimates contained and referenced herein are well established, by their nature, mineral resource estimates are 
imprecise and depend, to a certain extent, upon statistical inferences which may ultimately prove unreliable. If such 
mineral resource estimates are inaccurate or are reduced in the future, this could have a material adverse impact on the 
Company. Due to the uncertainty that may be attached to inferred mineral resources, it cannot be assumed that all or any 
part of an inferred mineral resource will be upgraded to an indicated or measured mineral resource as a result of 
continued exploration. 
 
Any forward-looking information speaks only as of the date on which it is made and, except as may be required by 
applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking information, 
whether as a result of new information, future events or results or otherwise. 
 
 
 
 
FOR FURTHER INFORMATION PLEASE CONTACT: 
 
Orsu Metals Corporation 
Alexander Yakubchuk 
Director of Exploration and COO 
+44 (0) 20 7518 3999 
+44 (0)20 7518 3998 (FAX) 
info@orsumetals.com 
www.orsumetals.com 
 
OR 
 
Canaccord Genuity Limited 
Ryan Gaffney 
+44 (0) 20 7050 6500 
 
OR 
 
Vanguard Shareholder Solutions 
+ 1 604 608 0824 
 
 
Orsu Metals Corporation 
 

Orsu Metals (LSE:OSU)
Historical Stock Chart
From Jun 2024 to Jul 2024 Click Here for more Orsu Metals Charts.
Orsu Metals (LSE:OSU)
Historical Stock Chart
From Jul 2023 to Jul 2024 Click Here for more Orsu Metals Charts.