Liqhobong - Update (7463A)
February 07 2011 - 2:00AM
UK Regulatory
TIDMFDI
RNS Number : 7463A
Firestone Diamonds PLC
07 February 2011
Firestone Diamonds plc
Production to commence at Liqhobong Mine in February 2011
LONDON: 7 February, 2011
Firestone Diamonds plc, ("Firestone" or "the Company"), the
AIM-quoted diamond mining and exploration company (ticker:
AIM:FDI), is pleased to announce an update on developments at the
Company's Liqhobong Mine in Lesotho.
HIGHLIGHTS
-- Mining
- Detailed mine planning and scheduling completed
- Mining contractor appointed and earthmoving equipment
mobilised to site
- Mining to commence in February
- Mining initially focused on high grade K5 and
K6 kimberlite units
-- Production Plant 1
- Wet commissioning completed in January 2011 and
ready for first delivery of ore
- Expected to achieve rated production capacity
of 0.4 mtpa on schedule by March 2011
- Capacity to be tripled to 1.3 mtpa by Q4 2011
- Expected to generate revenue of $43 million per
annum at full capacity
-- Production Plant 2
- Work continuing on specifications and design for
Plant 2, with planned capacity of 4.2 mtpa and
expected revenue of $140 million per annum
In December 2010, Firestone announced that it had raised GBP13
million through an equity placing, the proceeds of which were
principally to be used to accelerate the Company's plans to
recommence and significantly expand production at the Main Pipe at
its 75% owned Liqhobong Mine in Lesotho. Good progress has been
made at Liqhobong since December and production is expected to
recommence ahead of schedule in February 2011.
A resource of 91 million tonnes at an average grade of 34 carats
per hundred tonnes containing 31 million carats has been identified
at the Main Pipe. With an average estimated diamond value of
$98/carat and a contained value of approximately $3 billion,
Liqhobong is considered by the Company to be one of the most
attractive undeveloped kimberlites in the world.
Philip Kenny, CEO of Firestone Diamonds, commented: "We are
pleased with the very rapid progress that we have made at
Liqhobong, which we believe has the potential to be a highly
profitable mining operation. Together with production from the BK11
mine and our extensive portfolio of kimberlites in Botswana, we
believe that Firestone is now very well positioned to become a
significant diamond producer and to reach its target of producing 1
million carats per annum by 2014."
Mining
Initial mine planning studies undertaken by the Company in 2010
indicated that open pit mining operations can be undertaken to a
depth of 390 metres and would result in the mining of approximately
60 million tonnes of kimberlite and the production of an estimated
19 million carats over a period of approximately 17 years. These
numbers are likely to increase following the increase in diamond
valuation for Liqhobong from $86/carat to $98/carat in December
2010.
An experienced Lesotho-based mining contractor has been
appointed to manage mining operations at Liqhobong. The contractor
has mobilised the earthmoving equipment required to recommence
mining operations and this equipment arrived on site at the
beginning of February 2011. Mining operations are expected to
commence in February 2011. It is expected that much of the mining
planned in 2011 can be undertaken without blasting, so a blasting
contractor will only be mobilised to site when required later in
the year.
Detailed mine planning and scheduling was completed in January
2011 in preparation for the recommencement of operations. Mining
operations will initially be focused on the K5 and K6 kimberlite
units, which are the highest grade units in the Main Pipe and are
considered, based on recoveries from previous mining operations, to
have the highest potential to yield large, high value diamonds.
Production Plant
Plant 1
Wet commissioning of Plant 1 was completed in January 2011 and
the plant is ready for the first delivery of ore for treatment. It
is expected that the plant will achieve its current rated
production capacity of 0.4 million tonnes per annum ("mtpa") on
schedule in March 2011.
Work on the proposed expansion of Plant 1, which will triple
production capacity to 1.3 mtpa commenced in January 2011, and the
Company expects the expansion to be completed on schedule in Q4
2011. At full capacity of 1.3 mtpa Plant 1 is expected to generate
revenue of $43 million per annum, based on the average price
achieved in December 2010 for Liqhobong diamonds of $98/carat.
Capital costs for the Plant 1 expansion work are estimated to be $9
million, which will be financed from the proceeds of the December
2010 placing.
Plant 2
Work is continuing on the specifications and design for Plant 2,
which is planned to have a capacity of 4.2 mtpa, and these will be
finalised later in 2011 using data from the operation of Plant 1.
It is expected that the decision to commence construction of Plant
2 will be made in 2012, with initial production expected to
commence in 2013. At full production Plant 2 is expected to
generate revenue of $140 million per annum.
Labour and mine infrastructure
Planning commenced in December 2010 for the sourcing of staff.
All of the labour required to support the recommencement of
operations at Liqhobong has now been mobilised to site. Work on
upgrading the access road to Liqhobong commenced in January 2011
and is still ongoing.
For further information, visit the Company's web site at
www.firestonediamonds.com or contact:
+44 20 8834 1028/+44 7831
Philip Kenny, Firestone Diamonds 324 645
Tim Redfern, Evolution Securities
(Joint Broker) +44 20 7071 4312
Rory Scott, Mirabaud Securities
(Joint Broker) +44 20 7878 3360
Alexander Dewar, Brewin Dolphin
(Nominated Adviser) +44 131 529 0276
Jos Simson / Leesa Peters, Tavistock +44 20 7920 3150/+44 7899
Communications 870 450
Background information on Firestone Diamonds:
Firestone Diamonds plc is an international diamond mining and
exploration company with operations focused on Lesotho and
Botswana. Firestone operates the Liqhobong Mine in Lesotho and the
BK11 Mine in Botswana. Firestone is also the largest holder of
mineral rights in Botswana's diamondiferous kimberlite fields,
controlling approximately 10,000 square kilometres around the major
Orapa and Jwaneng mines and the entire Tsabong kimberlite field. In
addition to Liqhobong and BK11, Firestone has 108 kimberlites in
its portfolio, of which 30 have been proven to be
diamondiferous.
Lesotho is emerging as one of Africa's significant new diamond
producers and hosts Gem Diamonds' Letseng Mine, Firestone's
Liqhobong Mine as well as the Kao and Mothae development projects.
Botswana is the world's largest and lowest cost producer of
diamonds, with annual production worth over $2.5 billion, and is
considered to be one of the most prospective countries in the world
to explore for diamonds.
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCBLGDDRUGBGBS
Firestone Diamonds (LSE:FDI)
Historical Stock Chart
From Jun 2024 to Jul 2024
Firestone Diamonds (LSE:FDI)
Historical Stock Chart
From Jul 2023 to Jul 2024