Ivanhoe Mines (TSX: IVN)(NYSE: IVN)(NASDAQ: IVN) today announced
its results for the quarter ended June 30, 2011. All figures are in
US dollars, unless otherwise stated.
HIGHLIGHTS DURING THE QUARTER AND SUBSEQUENT WEEKS
-- Overall construction at Oyu Tolgoi continues to advance on schedule and
on budget, and reached a 30.8% level of completion at the end of Q2. Key
elements of the project, including the concentrator complex, primary
crusher and tailings-thickening ponds, remain ahead of schedule.
Commercial production is expected to commence in the first half of 2013.
-- Pre-stripping for the phase-one, open-pit mine on the gold-rich Southern
Oyu deposits at Oyu Tolgoi began in August 2011. A ground-breaking
ceremony for the open pit was held to officially mark the commencement
of pre-stripping operations.
-- The development of the first lift of the phase-two, underground block-
cave mine at the Hugo North Deposit continued successfully during Q2'11.
Lateral mine development 1,300 metres below surface at Hugo North is on
schedule, achieving an advance during Q2'11 of 1,190 metres, for a total
of 7,939 metres completed since tunneling started in 2008.
-- Official approvals were received in early May 2011 that enabled the Oyu
Tolgoi Project to begin construction of a 95-kilometre, high-voltage
power transmission line to deliver electricity expected to be imported
from China to supply the initial mining operation. The erection of
towers for the 220-kilovolt transmission line in Mongolia is expected to
be completed later this year and the line stringing is planned for
spring 2012 to coincide with anticipated stringing on the Chinese side
of the border.
-- Contract negotiations for the supply and sale of copper-gold-silver
concentrate to be produced at Oyu Tolgoi are expected to be finalized in
Q4'11. Most of the concentrate initially is expected to be delivered to
smelters in China.
-- Oyu Tolgoi's site-based construction workforce totalled approximately
14,200 at the end of July 2011, with approximately 11,200 working on
site each day and the balance on leave. Approximately 7,320 Mongolians
were employed at the Oyu Tolgoi site, with an additional 3,500
Mongolians participating in offsite training.
-- On July 12, Ivanhoe Mines and BHP Billiton Ltd. began a new exploration
drilling program on their copper-molybdenum-gold discovery at the Ulaan
Khud North joint-venture licence, approximately 10 kilometres north of
Oyu Tolgoi. The first drill hole, UKD056, is planned to test its target
to a depth of 1,100 metres.
-- During Q2'11, Ivanhoe Mines' 57%-owned subsidiary, SouthGobi Resources
(TSX: SGQ)(SEHK: 1878), reported coal sales of $47.3 million from its
Ovoot Tolgoi mine in southern Mongolia, representing approximately 1.05
million tonnes of coal sold to customers in China at an average realized
price of approximately $54 per tonne.
-- Ivanhoe Mines' 62%-owned subsidiary, Ivanhoe Australia (TSX: IVA)
(ASX: IVA), continued to focus on the development of its Merlin
high-grade molybdenum and rhenium project in the Cloncurry region of
Queensland. Construction of the decline to access the Merlin and Little
Wizard deposits had progressed to 1,097 metres by the end of Q2'11.
-- Altynalmas Gold, 50%-owned by Ivanhoe Mines, is continuing its drilling
program designed to further delineate resources and reserves to NI 43-
101 standards at the Kyzyl Gold Project in Kazakhstan.
MONGOLIA
OYU TOLGOI COPPER-GOLD-SILVER PROJECT (66%-owned by Ivanhoe
Mines)
Construction of the Oyu Tolgoi copper-gold-silver complex
advancing toward planned start of commercial production in the
first half of 2013
The Oyu Tolgoi Project initially is being developed as an
open-pit operation, with the first phase of mining planned to start
at the near-surface Southern Oyu deposits, which include Southwest
Oyu and Central Oyu. A copper concentrator plant, related
facilities and necessary infrastructure that will support an
initial throughput of 100,000 tonnes of ore per day are being
constructed to process ore scheduled to be mined from the Southern
Oyu open pit. Commercial production of copper-gold-silver
concentrate is projected to begin in the first half of 2013.
Along with the surface activities, an 85,000-tonne-per-day
underground block-cave mine also is being developed at the Hugo
North Deposit, with initial production expected to begin in 2015.
The throughput capacity of the concentrator plant is expected to be
expanded to approximately 160,000 tonnes of ore per day when the
underground mine begins production.
Fluor Corporation is in charge of overall Oyu Tolgoi program
management, as well as services related to engineering, procurement
and construction management for the ore processing plant and
mine-related infrastructure, such as roads, water supply, a
regional airport and administration buildings.
Current operations activities related to the phase-one
concentrator are focused on finalizing the operational readiness
plan. Detailed commissioning, operation and maintenance plans are
being developed for all the components of the concentrator
circuits. Representatives of various manufacturers and engineering
groups are assisting with the preparation of the operational
readiness plan. At the open pit, assembly of the mining fleet is
continuing. Pre-stripping for the open-pit mine began in early
August 2011.
In early May 2011, the Oyu Tolgoi Project received the final
approvals required to proceed with construction of a 220-kilovolt
power transmission line from Oyu Tolgoi along a 95-kilometre route
south to the Mongolia-China international border. The construction
approval from Mongolia's Energy Regulatory Authority and a land-use
contract from the governor of Khanbogd soum (township), which
includes Oyu Tolgoi, are key to the plan to import electricity from
China to operate the Oyu Tolgoi complex during its initial four
years of commercial production. Contracts have been awarded to
Mongolian companies for construction of the power transmission line
to the border. Tower construction is scheduled for completion
during Q4'11, with line stringing expected to commence in spring
2012. The transmission line is planned to be extended south of the
border by Chinese contractors to tie into the neighbouring Inner
Mongolian electrical grid.
Discussions between the Mongolian and Chinese governments were
held during Q2'11 and are expected to continue in Q3'11 to conclude
a bilateral agreement that would secure the supply of electrical
power from China. Subject to negotiations and final agreement, the
remaining permits, commercial arrangements and power-purchase
tariffs are expected to be expedited to ensure that imported power
will be available at the Oyu Tolgoi site by Q3'12. In the meantime,
additional diesel-powered generating capacity has been approved to
meet the project's requirements during the remaining stages of
construction.
Overall construction of the Oyu Tolgoi Project was 30.8%
complete at the end of Q2
Overall construction reached a 30.8% level of completion at the
end of Q2'11. Total capital invested in the project by the end of
Q2'11 was $2.5 billion.
Major updates for Q2'11 and plans for Q3'11 include:
-- Pre-stripping, as part of the construction of the phase-one open-pit
mine to recover ore from the Southern Oyu deposits, began in early
August 2011.
-- The development of the first lift of the phase two, underground block-
cave mine at the Hugo North Deposit continued successfully during Q2'11.
Lateral mine development 1,300 metres below surface at Hugo North is on
schedule, achieving an advance during Q2'11 of 1,190 metres, for a total
of 7,939 metres completed since tunneling started in 2008.
-- Construction progress on the concentrator and primary crusher is
continuing ahead of schedule. The concentrator was 37.8% complete at the
end of Q2'11, ahead of the plan of 35.8%. The primary crusher achieved
its final lift for the foundation and work on the coarse-ore storage
facility, conveyors and tailings thickeners also is making good
progress. Work has begun on the tailings storage facility and exterior
cladding of the concentrator shell is well advanced.
-- Construction of the headframe at Shaft #2 resumed in early August and
sinking is expected to start in Q4'11. Works are progressing to schedule
on the ancillary facilities associated with the sinking and construction
of the shaft.
-- A Russian ban on exports of diesel fuel, including those to Mongolia,
was in place during May and early June 2011. Russia provides more than
90% of Mongolia's diesel fuel. Oyu Tolgoi successfully managed this
supply shortage through rationing and securing a nine-million-litre
offsite storage facility. A study will begin in Q3'11 to review options
to further expand onsite diesel storage to increase security of diesel
supply.
-- Contract negotiations are close to finalization for the supply and sale
of copper-gold-silver concentrate to be produced from the project. Most
of the concentrate initially is expected to be sold to smelters in
China. Final term sheets with smelters are expected to be finalized in
Q4'11.
-- Discussions are continuing with relevant government agencies on the
outbound copper concentrate logistics. Oyu Tolgoi is investigating the
ability to use large trailer-train trucks to increase efficiencies
across the Mongolia-China border.
Phase one construction on budget
In December 2010, Ivanhoe Mines announced that a $2.3 billion
capital budget had been approved for 2011 in what is the peak year
of construction activity on the first phase of the Oyu Tolgoi
Project. In addition to the $2.3 billion capital budget, approval
also was received for an additional $150 million budget for the
2011 Ulaanbaatar office operations and $100 million for the second
tax prepayment that was made to the Mongolian Government in June
2011. At the end of Q2'11, $1.4 billion of the 2011 budget had been
spent by the project, which was under the forecast of $1.5
billion.
Capital required from January 1, 2011, through to completion of
the phase-one, 100,000-tonne-per-day project and the commencement
of commercial production is expected to total approximately $4.5
billion. The 2011-2013 estimate of $4.5 billion includes
approximately $550 million in remaining contingencies and
escalation allowances although no provision has been made for
foreign exchange variances or cost increases on construction
commitments that may be incurred.
Capital invested in phase-one construction to support future
expansion
The engineering and construction stages have recognized the need
to accommodate a major increase in ore-processing capacity in the
future while minimizing potential disruption to operations that
will be underway at that time.
Wherever possible, Oyu Tolgoi has taken the opportunity to allow
for expansion with minimal impact on operations. Oyu Tolgoi's plans
call for initial production of 100,000 tonnes of ore per day, which
is expected to increase to between 150,000 and 160,000 tonnes per
day when ore from the underground mine becomes available. To
facilitate this expansion, Oyu Tolgoi has constructed a third
ore-reclaim tunnel that will increase the capacity to feed ore to
the concentrator by 50-60% over the initial rate of production. To
cater to future increased production, a pipeline has been installed
that, with minor modifications, could supply water for processing
up to 160,000 tonnes a day. Oyu Tolgoi also has allowed for
expansion in the concentrator by adding space in the flotation area
and installing other equipment to handle higher production rates.
Studies examining options to process additional ore are
ongoing.
Rio Tinto working with Ivanhoe Mines to complete international
project-finance package of up to $4.0 billion
Ivanhoe Mines, Rio Tinto, a core lending group and their
advisers are working together to finalize an approximate $4.0
billion project-finance facility for the Oyu Tolgoi Project; their
objective is to sign loan documentation by the end of this
year.
The initial core lending group of Mandated Lead Arrangers is
comprised of European Bank for Reconstruction and Development,
International Finance Corporation, Export Development Canada, BNP
Paribas and Standard Chartered Bank. USExim Bank - together with
its adviser, Standard Bank - MIGA and EFIC recently joined the
lender group and have commenced their due diligence process with a
view to supporting the financing.
Recent meetings with lenders also were attended by Erdenes MGL
LLC (the Mongolian state-owned shareholder that owns 34% of Oyu
Tolgoi LLC) and representatives from Oyu Tolgoi LLC.
A term sheet outlining the main terms and conditions common to
all lenders is well advanced. Lenders have built a financial model
and are expected to finalize their technical, marketing, financial,
legal, insurance, environmental and social due diligence later this
year. When loan documentation is agreed upon and signed, drawdowns
will be subject to conditions precedent currently being
negotiated.
Prior to first drawdown, it is expected that Ivanhoe Mines may
utilize a $1.8 billion interim funding facility to be provided by
Rio Tinto as bridge financing. This facility will be repaid from
the first drawdown of the project finance facility.
Final terms of a third-party project-finance facility for the
Oyu Tolgoi Project remain subject to the approval of the Oyu Tolgoi
LLC Board of Directors, the Ivanhoe Mines Board of Directors and
the joint Ivanhoe Mines-Rio Tinto Technical Committee.
Skills training and community programs well advanced
The Oyu Tolgoi Project's staffing strategy relies heavily on the
utilization of Mongolian nationals being developed and trained
during ongoing construction activities. At end of July 2011,
approximately 7,320 Mongolians were working on the project at the
development site. In addition, more than 3,500 Mongolians were
participating in offsite training. Oyu Tolgoi has committed more
than $58 million in funding over five years toward technical and
vocational training in Mongolia.
Oyu Tolgoi launched a local herder procurement support program
aimed at providing financial assistance and mandated procurement of
goods and services from herders in communities surrounding the mine
area. As part of this program, two water wells were drilled for
households located close to the Gunii Khooloi deep underground
aquifer. An opening ceremony was held at the Dalanzadgad supplier
training, evaluation and development centre that Oyu Tolgoi has
funded to provide business incubation services for South Gobi
entrepreneurs. More than 150 South Gobi suppliers and entrepreneurs
are supplying goods and services to Oyu Tolgoi, which is an
increase of 300% in just 12 months.
Third agreed prepayment of Mongolian taxes made in Q2
On June 7, 2011, Ivanhoe Mines and Oyu Tolgoi LLC made the third
and final prepayment to the Government of Mongolia in a ceremony
held in Ulaanbaatar and attended by senior project representatives
and government cabinet ministers. The $100 million prepayment,
which was due by June 30 this year, completed a total prepayment
package of $250 million that was an attendant arrangement to the
long-term Oyu Tolgoi Investment Agreement signed in October 2009.
Together with the second prepayment of $50 million made after the
Investment Agreement took effect March 31, 2010, the third
prepayment will accrue interest at the rate of 1.59% after tax and
will be credited against the project's future taxes and royalties
beginning January 2012. The first payment of $100 million was made
by Oyu Tolgoi LLC at the time the Investment Agreement was signed,
in October 2009, through the purchase of a Treasury Bill from the
government that had a face value of $115 million payable within
five years after issuance.
Ivanhoe Mines signs Amended and Restated Shareholders'
Agreement
In June 2011, Ivanhoe Mines and Rio Tinto agreed with the
Mongolian government to execute the Amended and Restated
Shareholders' Agreement, which provided limited amendments to the
Oyu Tolgoi Shareholders' Agreement that was signed in conjunction
with the Investment Agreement in October 2009. Ivanhoe Mines is
funding the Mongolian government's 34% share of the project's
initial capital costs. The interest rate to be applied to the
repayment of the government's share of the costs for amounts
incurred after January 31, 2011, has been reduced to LIBOR plus
6.5%, down from the previous rate of 9.9%, adjusted for the US CPI.
The interest-rate adjustment was made at the government's request
and took into consideration the higher costs of capital that
prevailed in 2009 following the global economic crisis.
Exploration drilling continued in Q2'11
During Q2'11, Ivanhoe Mines continued its drilling program on
the Oyu Tolgoi Project with 10,279 metres of surface resource
geology drilling (including geotechnical and mine-development
investigation holes), 2,680 metres of underground geotechnical
drilling and 5,280 metres of surface exploration diamond
drilling.
Exploration drilling is ongoing at Heruga North. Hole OTD1510D
included a 374-metre intercept, from 1,498 to 1,872 metres down
hole, that graded 0.26 grams of gold per tonne, 0.56% copper and 86
ppm molybdenum on the eastern flank of Heruga North (including a
158-metre interval, from 1,646 to 1,804 metres, that graded 0.37
g/t gold, 0.71% copper and 125 ppm molybdenum, or 1.01% copper
equivalent) and ended before reaching the western mineralized zone
in unmineralized quartz monzodiorite, at 2,736 metres down hole.
OTD1510E is a daughter hole off OTD1510D and is designed to further
test the eastern flank of the quartz monzodiorite, where
bornite-rich mineralization is thought to occur, similar to earlier
discoveries in the Hugo Dummett ore body. OTD1569, an infill hole
between the Heruga Deposit and Heruga North 200 metres to the south
of the OTD1510 section, was lost in moderate-grade copper
mineralization at 1,848 metres after passing through a 350-metre
section of moderate-to-weak mineralization. Assay results are
pending.
A total of 1,815 metres of drilling was completed on the Shivee
Tolgoi licence. Hole EGD154 currently is testing the northern
extension to the Hugo Dummett ore body, some 150 metres north of
the last significant mineralization.
Detailed geological mapping is continuing in the area around the
Javkhlant prospect at the southwestern end of the Oyu Tolgoi
mineralized trend.
Exploration at Ulaan Khud North (50% owned)
New copper-molybdenum-gold zone discovered on Ivanhoe-BHP
Billiton joint-venture licence
In March 2011, Ivanhoe Mines announced that Ivanhoe Mines and
BHP Billiton Ltd. had discovered a new zone of shallow
copper-molybdenum-gold mineralization approximately 10 kilometres
north of the Oyu Tolgoi Project. The discovery, known as Ulaan Khud
North, extended the known strike length of the Oyu Tolgoi
mineralized system by an additional three kilometres to the north,
to a new total of more than 23 kilometres.
Ulaan Khud North is located on a 19,625-hectare exploration
licence that is part of Ivanhoe Mines' joint-venture partnership
with BHP Billiton, formed in 2005. BHP Billiton has earned a 50%
interest in the joint venture, which includes the Ulaan Khud North
property, by spending $8 million in exploration costs and
conducting an airborne survey using BHP Billiton's proprietary
Falcon™ gravity gradiometer system over the Oyu Tolgoi area.
A Pre-Mining Agreement for the Ulaan Khud licence was received
from the Government of Mongolia in March 2011. It specifies that
Ivanhoe Mines and BHP Billiton have three years to conduct
additional exploration, complete an environmental impact study,
prepare a final feasibility study and gain approval for the design
for the project. The agreement also specifies that a Technical and
Economical Study to mine the deposit is required to be delivered to
the Mineral Resources Authority of Mongolia by June 30, 2013.
Drilling commenced on the first target on July 12, 2011. Hole
UKD056 is designed to test the first target to a depth of 1,100
metres.
MONGOLIA
SOUTHGOBI RESOURCES (57% owned)
Ongoing expansion of SouthGobi's Ovoot Tolgoi coal mine
SouthGobi continues to mine and sell coal produced at its Ovoot
Tolgoi Mine in Mongolia's South Gobi Region, approximately 40
kilometres north of the Shivee Khuren-Ceke crossing at the
Mongolia-China border.
In Q2'11, SouthGobi had sales of approximately 1.05 million
tonnes at an average realized price of approximately $54 per tonne.
This was an improvement over the sale of approximately 450,000
tonnes in Q2'10 at an average realized selling price of $43 per
tonne. Revenue increased from $17.7 million in Q2'10 to $47.3
million in Q2'11, due to the higher realized average prices and
higher sales volume.
SouthGobi's revenues are net of royalties. SouthGobi is subject
to a 5% royalty on all coal sold based on a set reference price per
tonne that is published monthly by the Mongolian government.
Effective January 1, 2011, SouthGobi also became subject to a
sliding-scale royalty of up to 5% based on the set reference price
of coal. Based on the reference price for Q2'11, SouthGobi was
subject to a 3% sliding royalty in addition to the 5% base royalty.
The weighted average reference price for Q2'11 was $95 per
tonne.
Cost of sales of $49.7 million for Q2'11 was $36.5 million
higher than Q2'10 ($13.2 million). Cost of sales is comprised of
the cost of the product sold, inventory write-downs, mine
administration costs, equipment depreciation, depletion of
pre-production stripping costs and stock-based compensation costs.
The increase is due to the significantly higher sales volume,
higher diesel costs and a $10.6 million inventory write-down.
Mineral licence received for Soumber
On June 3, 2011, SouthGobi announced it had successfully
registered a resource associated with the Soumber Deposit with the
Mineral Resource Authority of Mongolia (MRAM) and on July 6, 2011,
SouthGobi announced that MRAM had issued SouthGobi a 10,993-hectare
mining licence. The new mining licence was granted for an initial
term of 30 years, with an option for two 20-year extensions.
AUSTRALIA
IVANHOE AUSTRALIA (62% owned)
Ivanhoe Australia's key projects, all situated on granted Mining
Leases, are Merlin, Mount Dore and Mount Elliott. During Q2'11,
work focused on progressing the Merlin pre-feasibility study and
decline, the copper-gold study, finalizing the Mount Dore
heap-leach scoping study and commencing underground work at the
Osborne and Kulthor deposits.
Ivanhoe Australia incurred exploration expenses of $43.0 million
in Q2'11, compared to $14.9 million in Q2'10. The $28.1 million
increase was largely due to work on the Merlin decline, work on the
underground at the Osborne and Kulthor deposits and work on the
various ongoing studies.
Merlin molybdenum and rhenium development study
The Merlin molybdenum and rhenium deposit is the lower-most
mineralized zone in the Mount Dore deposit and starts near the
surface and dips east at between 45 and 55 degrees. To date,
drilling has defined mineralization to vertical depths ranging from
60 to 580 metres and over a strike length of 1,000 metres. The
overall mineralized zone at Merlin has an average true width of 3.9
metres and ranges between two and 20 metres. The Little Wizard
Deposit represents the southern-most extent of the Merlin
molybdenum mineralization of economic interest found to date.
During Q2'11, Ivanhoe Australia focused on continuing the Merlin
pre-feasibility study, with further optimization work required on
the mining, flotation circuit and roaster design prior to
completion of the study. Ivanhoe Australia expects that the
requirement for further studies may result in the commencement of
Merlin production in late 2013. Ivanhoe Australia plans to
construct a purpose-built processing facility for Merlin and
expects to use the existing Osborne concentrator for the
copper-gold business.
At the end of Q2'11, construction of the Merlin decline was on
schedule and budget. The decline face had progressed to 1,097
metres and was adjacent to the Little Wizard deposit at the end of
Q2'11. Ivanhoe Australia plans to develop an access drive into the
Little Wizard deposit to undertake geotechnical tests to assess
potential mining methods and obtain bulk samples for metallurgical
test work.
Copper-gold study underway
During Q2'11, Ivanhoe Australia continued work on the
copper-gold study to identify potential ore feed for the Osborne
concentrator from the Kulthor, Osborne underground, Osborne open
pit and Starra 276 deposits. The study is assessing these near-term
production opportunities, including mining and processing
production rates and capital and operating cost profiles.
Ivanhoe Australia began underground work at Osborne and Kulthor
during Q2'11. By the end of Q2'11, a total of 296 metres were
advanced on both deposits. Access to Kulthor deposit is expected by
the end of August 2011.
Mount Dore scoping study
Ivanhoe Australia plans to complete a Preliminary Economic
Assessment (a NI 43-101-compliant report) for the Mount Dore copper
leach project in Q3'11.
Mount Elliott scoping study started
During Q2'11, Ivanhoe Australia continued work on the Mount
Elliott scoping study and plans to finalize the study in Q1'12. The
study plans to evaluate all mining options for the large-tonnage
deposit, including the potential to extract copper-gold ore from
the high-grade SWAN zone for processing at Osborne.
Regional exploration
During Q2'11, work focused on drilling copper-gold targets at
Houdini and along the Mount Dore trend. The drilling included
12,133 metres of diamond drilling and 654 metres of
reverse-circulation drilling.
Gain on investment in Exco
During Q2'11, Ivanhoe Australia recognized a gain of $45.7
million in relation to its investment in Exco Resources Limited
(Exco). Ivanhoe Australia owns approximately 22.8% of Exco. On June
30, 2011, Exco completed the sale of its Cloncurry Copper Project
to Xstrata Copper for A$175 million. Exco intends to return a
proportion of the proceeds to its shareholders. Ivanhoe Australia
expects to receive approximately A$30 million by the end of October
2011.
KAZAKHSTAN
Kyzyl Gold Project (50% owned)
Altynalmas Gold holds 100% ownership of the Kyzyl Gold Project
in northeastern Kazakhstan. The Kyzyl Gold Project contains the
Bakyrchik and Bolshevik gold deposits, as well as a number of
satellite deposits. Altynalmas Gold is proceeding to advance the
development of the Kyzyl Gold Project following the successful
completion of the pre-feasibility study in 2010.
New Bakyrchik East Mineral Resource Gold deposit boosts total
gold resources at Kyzyl Project
On August 3, 2011, Ivanhoe Mines announced a NI 43-101-compliant
Mineral Resource estimate for the new Bakyrchik East Deposit at the
Kyzyl Gold Project. The Mineral Gold Resources at Bakyrchik East
are hosted in two lenses comprised of more than 20 sub-zones that
collectively measure 2,000 metres along strike by 1,500 metres down
dip, extending from surface to a depth of 800 metres.
Roscoe Postle Associates Inc. (RPA), an internationally
recognized consulting firm, estimates the Bakyrchik East Deposit at
6.8 million tonnes of Inferred Mineral Resources grading 6.0 grams
of gold per tonne, containing 1.3 million ounces of gold.
The Bakyrchik East Gold Deposit, consisting of the Globoki Log
and Promezhutochny zones, is located 800 metres east along strike
from the eastern edge of the main Bakyrchik Gold Deposit within the
Kyzyl Shear Zone. The RPA estimate is based on drilling results
that were available to July 11, 2011. Further details can be found
in Ivanhoe Mines' August 3, 2011 press release.
Exploration continuing with 60,000 metres of drilling
planned
Altynalmas Gold is continuing its drilling program designed to
further delineate resources and reserves at the Kyzyl Gold Project.
A total of 24,170 metres were drilled during Q2'11 on the Bakyrchik
Mining Lease (42,667 metres year to date). For the remainder of the
year, an additional 11,333 metres are planned to be drilled on the
Bakyrchik Mining Lease and a further 50,000 metres are planned to
begin the delineation of the numerous satellite deposits on the
surrounding exploration licence.
Recent drilling activities have been focused on exploring the
down-dip extensions of known gold resources, as well as on the
flanks of known gold lenses.
Feasibility study nearing completion
The definitive feasibility study on the Kyzyl Gold Project,
focusing on the Bakyrchik Deposit, which began in 2010 is nearing
completion and is expected to be issued in Q4'11. Additional test
work and verification of the process of stabilization of wastes
containing arsenic that are generated during the roasting of
sulphide ore are required prior to the issuance of the study.
OTHER DEVELOPMENTS
Rio Tinto's stake in Ivanhoe Mines increases to 46.5%
In June 2011, Ivanhoe Mines received $501.6 million from Rio
Tinto following Rio Tinto's decision to exercise all remaining
share-purchase warrants that it holds in Ivanhoe Mines. Rio Tinto
exercised all the remaining Series B and Series C warrants that it
was granted as part of the 2006 and 2007 financing agreements
associated with Rio Tinto's original investment in Ivanhoe Mines.
The additional shares increased Rio Tinto's ownership stake in
Ivanhoe Mines from 42.0% to 46.5%.
The $501.6 million from the exercise of the warrants is being
applied toward the construction of the first phase of the Oyu
Tolgoi copper-gold-silver complex.
The increased level of ownership entitled Rio Tinto to nominate
one additional director to the 14-member Ivanhoe Mines board,
increasing to seven the total number of Ivanhoe Mines directors
nominated by Rio Tinto. On July 14, 2011, Dan Larsen, Rio Tinto's
Controller and Global Head of Planning and Reporting, was appointed
to the Ivanhoe Mines board. Howard Balloch, a director of Ivanhoe
Mines since 2005, relinquished his position to enable Mr. Larsen's
nomination.
Including proceeds from the warrants, Rio Tinto's combined
investment in Ivanhoe Mines since October 2006 amounts to $3.5
billion through the purchase of shares, the exercise of warrants
and a converted debt facility.
The maximum level of ownership interest in Ivanhoe Mines that
Rio Tinto may achieve - through the exercise of its right to
subscribe, from time to time, for additional Ivanhoe Mines shares
and permitted open market purchases of common shares - is capped at
49% until the current standstill limitation expires on January 18,
2012.
Arbitration update
The arbitration proceeding between Ivanhoe Mines and Rio Tinto
regarding Ivanhoe Mines' Shareholders' Rights Plan resumed during
June 2011 following the expiry of a six-month suspension that was
agreed upon by the companies as part of the Heads of Agreement
signed in December 2010.
Ivanhoe Mines is confident that the rights plan, overwhelmingly
supported by 95% of the votes cast by its minority shareholders
more than a year ago, is not in breach of any of Rio Tinto's
existing contractual rights. Ivanhoe Mines is committed to
vigorously protecting the rights of all of its shareholders and has
received very strong support from institutional shareholders for
its insistence that all shareholders be treated fairly during any
takeover bid.
Ivanhoe Mines submitted a statement of defence in October 2010
that rejected Rio Tinto's claim and also filed a counter-claim
contending that Rio Tinto had breached certain covenants in its
October 2006 private placement agreement with Ivanhoe Mines. Rio
Tinto has filed a statement of defence to the Ivanhoe Mines
counterclaim.
Financial Results
In Q2'11, Ivanhoe Mines recorded net income of $0.6 million
($0.00 per share), compared to a net loss of $30.0 million ($0.06
per share) in Q2'10, which was an increase of $30.6 million.
Results for Q2'11 mainly were affected by $68.6 million in
exploration expenses, $49.7 million in cost of sales, $19.5 million
in general and administrative expenses and $3.3 million in interest
expense. These amounts were offset by coal revenue of $47.3
million, a $70.4 million change in the fair value of embedded
derivatives, a $44.8 million in share of gain of significantly
influenced investees, $4.9 million in interest income and $2.3
million in mainly unrealized foreign exchange gains.
Exploration expenses of $68.6 million in Q2'11 increased $29.1
million from $39.5 million in Q2'10. Exploration expenses included
$22.8 million spent in Mongolia ($23.2 million in Q2'10), primarily
for Oyu Tolgoi and Ovoot Tolgoi, and $43.0 million incurred by
Ivanhoe Australia ($14.9 million in Q2'10). Exploration costs are
charged to operations in the period incurred and often represent
the bulk of Ivanhoe Mines' operating loss for that period.
Ivanhoe Mines' cash position, on a consolidated basis at June
30, 2011, was $1.6 billion. As at August 12, 2011, Ivanhoe Mines'
consolidated cash position was approximately $1.3 billion.
SELECTED QUARTERLY DATA
This selected financial information is in accordance with U.S. GAAP.
($ in millions of dollars, except per share information)
Quarter Ended
--------------------------------
Jun-30 Mar-31 Dec-31 Sep-30
2011 2011 2010 2010
---------------------------------------------------------------------------
Revenue $47.3 $20.2 $41.6 $6.6
Cost of sales (49.7) (20.3) (46.4) (14.9)
Exploration expenses (68.6) (46.2) (59.6) (48.1)
General and administrative (19.5) (25.3) (46.4) (15.0)
Foreign exchange gains (losses) 2.3 3.2 6.6 5.3
Change in fair value of derivative - (432.5) 135.7 -
Change in fair value of embedded
derivatives 70.4 (36.8) (20.0) 49.8
Net income (loss) from continuing
operations 0.6 (492.5) 37.3 (24.9)
Income (loss) from discontinued operations - - - -
Net income (loss) 0.6 (492.5) 37.3 (24.9)
Net income (loss) per share - basic
Continuing operations $0.00 ($0.79) $0.07 ($0.05)
Discontinued operations $0.00 $0.00 $0.00 $0.00
Total $0.00 ($0.79) $0.07 ($0.05)
Net income (loss) per share - diluted
Continuing operations $0.00 ($0.79) $0.06 ($0.05)
Discontinued operations $0.00 $0.00 $0.00 $0.00
Total $0.00 ($0.79) $0.06 ($0.05)
---------------------------------------------------------------------------
Quarter Ended
--------------------------------
Jun-30 Mar-31 Dec-31 Sep-30
2010 2010 2009 2009
---------------------------------------------------------------------------
Revenue $17.7 $13.9 $9.9 $11.9
Cost of sales (13.2) (20.3) (8.5) (8.6)
Exploration expenses (39.5) (71.4) (67.2) (40.9)
General and administrative (14.7) (8.3) (15.0) (12.5)
Foreign exchange gains (losses) (4.9) 1.7 2.2 19.5
Change in fair value of embedded
derivatives 72.2 (1.4) (45.0) -
Loss on conversion of convertible credit
facility - (154.3) - -
Net income (loss) from continuing
operations (30.0) (200.5) (138.7) (47.8)
Income (loss) from discontinued operations - 6.6 9.2 (21.9)
Net income (loss) (30.0) (193.9) (129.5) (69.8)
Net income (loss) per share - basic
Continuing operations ($0.06) ($0.44) ($0.32) ($0.12)
Discontinued operations $0.00 $0.01 $0.02 ($0.05)
Total ($0.06) ($0.43) ($0.30) ($0.17)
Net income (loss) per share - diluted
Continuing operations ($0.06) ($0.44) ($0.32) ($0.12)
Discontinued operations $0.00 $0.01 $0.02 ($0.05)
Total ($0.06) ($0.43) ($0.30) ($0.17)
---------------------------------------------------------------------------
Ivanhoe Mines' results for the three months ended June 30, 2011,
are contained in the unaudited Consolidated Financial Statements
and Management's Discussion and Analysis of Financial Condition and
Results of Operations, available on the SEDAR website at
www.sedar.com and Ivanhoe Mines' website at
www.ivanhoemines.com.
Ivanhoe Mines shares are listed on the Toronto, New York and
NASDAQ stock exchanges under the symbol IVN.
QUALIFIED PERSON
Disclosures of a scientific or technical nature in this release
and the Company's MD&A in respect to the Oyu Tolgoi Project
were prepared by, or under the supervision of, Stephen Torr, P.
Geo., an employee of the company and a qualified person as defined
in NI 43-101.
FORWARD-LOOKING STATEMENTS
Certain statements made herein, including statements relating to
matters that are not historical facts and statements of our
beliefs, intentions and expectations about developments, results
and events which will or may occur in the future, constitute
"forward-looking information" within the meaning of applicable
Canadian securities legislation and "forward-looking statements"
within the meaning of the "safe harbor" provisions of the United
States Private Securities Litigation Reform Act of 1995.
Forward-looking information and statements are typically identified
by words such as "anticipate", "could", "should", "expect", "seek",
"may", "intend", "likely", "plan", "estimate", "will", "believe"
and similar expressions suggesting future outcomes or statements
regarding an outlook. These include, but are not limited to:
statements respecting anticipated business activities; planned
expenditures; corporate strategies; proposed acquisitions and
dispositions of assets; discussions with third parties respecting
material agreements; the schedule for carrying out and completing
construction of the Oyu Tolgoi Project; the expansion of throughput
capacity of the concentrator, and the progress of construction of
the primary crusher, tailings thickening ponds and Shaft #2 at the
Oyu Tolgoi Project; the timing of replacing the construction fleet
with a mining fleet at the Oyu Tolgoi Project; the estimated
delivery of
the first ores from the Southern Oyu open pit to the
concentrator; the estimated schedule to bring the Oyu Tolgoi
Project into commercial production; statements related to the
anticipated capital costs of the Oyu Tolgoi Project; the
anticipated return to the original infrastructure progress timing
and a conclusion to the competitive bidding process for main
infrastructure works; the expected timing of production from the
first lift of the Hugo North block-cave mine; possible expansion
scenarios for the Oyu Tolgoi Project; the expected timing of
construction of the electrical transmission power line from the Oyu
Tolgoi Project to the Chinese border; the timing and outcome of
discussions between the Mongolian and Chinese governments regarding
importing electrical power from China; the progress of the
electrical power transmission line within Mongolia; the development
of alternative power generation arrangements relating to the Oyu
Tolgoi Project if a timely agreement to secure electrical power
from China is not secured by the Mongolian Government; the schedule
of receipt of permits from the Mongolian Government relating to
land use, permanent airport and roads; contract negotiations and
expected markets for concentrate produced at the Oyu Tolgoi
Project; initial production estimates; the commencement of
construction of the water pipeline and paved road to the Oyu Tolgoi
Project; the Oyu Tolgoi Project's anticipated yearly production of
copper and gold; the ability of Ivanhoe Mines to arrange acceptable
financing commitments for the Oyu Tolgoi Project and the timing of
such commitments; implementation of the Oyu Tolgoi Project's
training and development strategy; statements concerning
mineralization potential and planned drilling activities at Ulaan
Khud North; target milling rates, mining plans and production
forecasts for the coal mine at Ovoot Tolgoi, Mongolia; the schedule
for carrying out and completing an expansion of the production
capability of the Ovoot Tolgoi Coal Project; the elements of
SouthGobi's planned exploration program for 2011; anticipated
outcomes with respect to the ongoing marketing of coal products
from the Ovoot Tolgoi Coal Project; the anticipated timing of
payback of capital invested in the Ovoot Tolgoi Coal Project; the
statements concerning the timing of commencement of commercial
operation and operating capacity of the Ceke to Linhe railway line;
the statements concerning the expected timing of construction and
the intended capacity of the planned paved highway from Ovoot
Tolgoi to the Mongolia-China border; the statements concerning the
timing of the expected completion of the Ovoot Tolgoi coal-handling
facility by mid-2012; the statements concerning SouthGobi's
expected coal sales and prices in Q3'11; the statements concerning
the timing of the Merlin pre-feasibility study; the statements
concerning the development and construction of
the Merlin Project; the statements concerning the anticipated
timing of the copper-gold study; the statements concerning the
anticipated timing of the Mount Dore preliminary economic
assessment and the Mount Elliott scoping study; timing of
receipt of expected proceeds from Exco's sale of Cloncurry
Copper Project; the statements that Altynalmas Gold's definitive
feasibility study is expected to be completed in Q4'11 and that it
will commence construction during 2011 on a roasting plant to
process refractory ore; planned drilling on the Bakyrchik Mining
Lease and the surrounding exploration licence; statements
respecting future equity investments in Ivanhoe Mines by Rio Tinto
and the intended use of such funds; Ivanhoe Mines' position that
its Shareholders' Rights Plan is not in breach of Rio Tinto's
existing contractual rights; the impact of amendments to the laws
of Mongolia and other countries in which Ivanhoe Mines carries on
business, particularly with respect to taxation; statements
concerning global economic expectations and future demand for
commodities; and the anticipated timing, cost and outcome of plans
to continue the development of non-core projects, and other
statements that are not historical facts.
Contacts: Ivanhoe Mines - Investors: Bill Trenaman
+1.604.688.5755 Ivanhoe Mines - Media: Bob Williamson
+1.604.688.5755 www.ivanhoemines.com
Ivanhoe Mines (NYSE:IVN)
Historical Stock Chart
From Jun 2024 to Jul 2024
Ivanhoe Mines (NYSE:IVN)
Historical Stock Chart
From Jul 2023 to Jul 2024