_PRESS RELEASE _
-
Nexans, in partnership with Swissgrid, will install a
high-voltage line in a road tunnel, a pioneering project in
Europe.
-
Works will begin in 2028 and be completed in
2030.
Paris, May 14, 2025 – Nexans, in partnership with
Swissgrid, Switzerland’s national grid operator, will install a
high-voltage line in the Saint-Gotthard Road tunnel.
The Saint-Gotthard Road tunnel’s second tube
will feature a first: by 2030, it will house an 18 km long
high-voltage line, which will replace the existing overhead line
across the pass. This new connection will play a critical role in
electricity transmission along Switzerland’s north–south
corridor.
The 220 kV high-voltage line is a pioneering
project. It marks a first of major significance in Europe: using a
road tunnel for cable installation. On behalf of the federal
government, Swissgrid evaluates every grid project to determine
whether synergies with other infrastructure—such as rail or road
tunnels—can be leveraged. Combining infrastructures often
contributes to landscape preservation and more efficient land use.
Nexans will supply a total of 57 km of extra-high voltage
cable for this operation, working with its bases in
Charleroi (Belgium), which will manufacture the cable, and in
Cortaillod (Switzerland), which will handle the project engineering
and installation as well as supply accessories. The preparatory
phase is set to unfold from 2025 to 2028, and works are due to
start in 2028 and be completed in 2030.
Nexans relied on a longstanding partnership with
Swissgrid, as well as the success of several previous projects.
This experience has enabled the company to acquire in-depth
knowledge of the Swiss market, along with a reputation for
excellence in reliability and installation solutions. Valued at
approximately €50 million, this project represents
the largest contract ever signed by Nexans Switzerland, making it a
historic milestone for the company.
Marco Spinelli, CEO PWR-Grid Central Europe at
Nexans, remarks, “This project illustrates our aim to remain a
top-tier partner for Swissgrid, leveraging our ability to devise
novel and dependable cable-laying solutions in complex
environments. It also reflects our commitment to supporting the
energy transition while playing an active part in protecting
landscapes.”
Once the new line is operational, the overhead
cables crossing the Gotthard Pass will be dismantled. However, four
pylons near the summit will remain active but be reduced in size,
to continue supporting a high-voltage connection for Swiss Federal
Railways (SBB). The dismantling operation will contribute to
reducing environmental and landscape impact in this sensitive
natural area.
About Nexans
For over a century, Nexans has played a crucial role in the
electrification of the planet and is committed to electrifying the
future. With approximately 28,500 people in 41 countries, the Group
is paving the way to a new world of safe, sustainable and
decarbonized electricity that is accessible to everyone. In 2024,
Nexans generated €7.1 billion in standard sales. The Group is a
leader in the design and manufacturing of cable systems and
services across four main business areas: PWR-Transmission,
PWR-Grid, PWR-Connect and Industry & Solutions. Nexans was the
first company in its industry to create a Foundation supporting
sustainable initiatives, bringing access to energy to disadvantaged
communities worldwide. The Group is recognized as a global
leader on climate action and has committed to Net-Zero emissions by
2050 aligned with the Science Based Targets initiative (SBTi).
Nexans. Electrify the Future.
Nexans is listed on Euronext Paris, compartment
A.
For more information, please visit
www.nexans.com
Contacts:
Communication
Mael Evin (Havas Paris)
Tel.: +33 (0)6 44 12 14 91
nexans_h@havas.com
Emmanuelle Guy
emmanuelle.guy@nexans.com |
Investor
relations
Audrey Bourgeois
Tel.: +33 (0)1 78 15 00 43
audrey.bourgeois@nexans.com
|
- Nexans to install Switzerland’s longest high-voltage
underground line - 1405
Nexans (TG:NXS)
Historical Stock Chart
From Jun 2025 to Jul 2025
Nexans (TG:NXS)
Historical Stock Chart
From Jul 2024 to Jul 2025