An announcement regarding power generation within China for the whole year of 2020 of Huaneng Power International, Inc. (the "Registrant"), made by
the Registrant on January 16, 2021.
Hong Kong Exchanges and Clearing Limited and The Stock Exchange of Hong Kong Limited take no
responsibility for the contents of this announcement, make no representation as to its accuracy or completeness and expressly disclaim any liability whatsoever for any loss howsoever arising from or in reliance upon the whole or any part of the
contents of this announcement.
ANNOUNCEMENT ON POWER GENERATION WITHIN
CHINA FOR THE WHOLE YEAR OF 2020
This announcement is made pursuant to Rule 13.10B of the Rules Governing the Listing of Securities on The Stock Exchange of Hong Kong Limited.
According to the preliminary statistics of Huaneng Power International, Inc., (the “Company”), in the fourth quarter of 2020, the Company’s total power generation by power plants within China on consolidated basis amounted to 110.410 billion kWh, representing an increase of
7.38% over the same period of 2019. Total electricity sold by the Company amounted to 103.979 billion kWh, representing an increase of 3.78% over the same period of 2019. In 2020, the Company’s total power generation by the power plants within
China on consolidated basis amounted to 404.016 billion kWh, representing a decrease of 0.24% over the same period of 2019. Total electricity sold by the Company amounted to 379.894 billion kWh, representing a decrease of 2.14% over the same period
of 2019. In 2020, the Company’s average on-grid electricity settlement price for its power plants within China amounted to RMB413.63 per MWh, representing a decrease of 0.81% over the same period of 2019. In 2020, the Company’s market based
electricity sold amounted to 221.405 billion kwh, with a ratio of 58.33% comparing to the corresponding total electricity sold, representing an increase of 1.93 percentage points over the same period of 2019.
The decrease in the Company’s power generation was mainly attributable to the following factors:
The power generations (in billion kWh) of the Company, by regions, are listed below:
For the fourth quarter of 2020, the power generation of Tuas Power Limited in Singapore, which is wholly-owned by the Company,
accounted for a market share of 21.2% in Singapore, representing a decrease of 0.2 percentage point compared to the same period of 2019. The accumulated power generation in 2020 accounted for a market share of 21.4%, representing an increase of 0.7
percentage point compared to the same period of 2019.
The Company put into operation the following projects in the fourth quarter: (Unit: MW)
In the fourth quarter of 2020, the Company completed the acquisition of the wind power assets of Shandong Huaneng Laizhou Wind Power Co., Ltd.
(53.25 MW), thereby increasing the Company's controlled installed capacity by 53.25 MW and the equity-based installed capacity by 42.6 MW.
In the fourth quarter of 2020, the operating life of Unit 2 (352 MW) of Huaneng Nantong Power Plant, Unit 4 (138 MW) and Unit
5 (138 MW) of Haikou Power Plant and Unit 1 (600 MW) of Tuas Power Plant has come to an end, and the shutdown procedures have been implemented. The above mentioned units are no longer included in the statistics of Company’s installed capacity.
In addition, the installed capacity of certain power plants invested by the Company changed in the fourth quarter of 2020.
Based on the above, as at 31 December 2020, the Company had a controlled installed capacity of 113,357 MW and an equity-based installed capacity
of 98,948 MW.