All amounts in US$ unless otherwise
indicated
Capstone Copper Corp. (“Capstone” or the “Company”)
(TSX:CS) today announced consolidated copper production for 2022
and provided operations and capital expenditure guidance for
2023.
Consolidated Copper Production for the nine-month period
April 1 to December 31, 2022
Capstone achieved its production and cost guidance for the
nine-month period ended December 31, 2022. Consolidated copper
production was 136.3 thousand tonnes at C1 cash costs1,2 of $2.68
per payable pound of copper produced. For Q4 2022, consolidated
copper production was 45.5 thousand tonnes at C1 cash costs1,2 of
$2.50 per payable pound of copper produced.
John MacKenzie, CEO of Capstone, commented, “We had a strong
finish to 2022 with consolidated cash costs down 9%
quarter-over-quarter, helped by cost control at our operations and
increased contribution of lower cost sulphide production. Our
growth in high-margin sulphide production will be significantly
boosted by the ramp-up of the Mantoverde Development Project next
year, a transformational project for Capstone that remains on
budget and on schedule for completion by year-end 2023.”
2023 Production and Costs Guidance
Copper Production
(‘000s tonnes)
C1 Cash
Costs1 (US$ per payable lb Cu Produced)
Sulphide Business
Pinto Valley
56.0 – 62.0
$2.40 – $2.60
Cozamin
23.0 – 25.0
$1.50 – $1.65
Mantos Blancos
45.0 – 51.0
$2.20 – $2.40
Total Sulphide
124.0 – 138.0
$2.15 – $2.35
Cathode Business
Mantos Blancos
10.0 – 12.0
$2.85 – $3.00
Mantoverde*
36.0 – 40.0
$3.50 – $3.70
Total Cathode
46.0 – 52.0
$3.35 – $3.55
Consolidated Cu Production
170.0 – 190.0
$2.50 – $2.70
*Mantoverde production shown on a 100%
basis
The Mantoverde Development Project is progressing well and
remains on track for commissioning and feeding first ore to the
mill in late 2023. Total projected capital cost remains unchanged
at $825 million.
Consolidated C1 cash costs1 are expected to decline in 2023
compared to 2022 due to an increased proportion of lower-cost
copper production from concentrates versus higher-cost copper
cathode. This will be driven primarily by increased throughput at
the Mantos Blancos concentrator, after the completion of the
ramp-up in 2022 of the Mantos Blancos Concentrator Debottlenecking
Project. The decline in 2023 cathode production is a result of the
anticipated grade decline in Mantoverde oxides. Helping offset
lower oxide grades are lower sulphuric acid prices, and we have
secured over 70% of our 2023 requirement at prices in the $130 -
$150 per tonne range, which is over $100 per tonne lower than
prices paid in 2022. Pinto Valley is expected to perform similarly
year-over-year for production and costs.
C1 cash costs1 at the Cozamin mine are expected to increase to
$1.50 to $1.65 per payable pound of copper produced. The additional
costs are expected with the operation of the new paste backfill and
dry stack tailings plant currently being commissioned and ramping
up. We are also introducing cut-and-fill mining in certain areas of
the mine this year. Some areas of the Mala Noche Footwall Zone will
benefit from this change in mining method which will increase the
realized mineral recovery in the mining process. A new technical
report will be issued at the end of Q1 2023 outlining the
incorporation of cut-and-fill to the mine plan. We anticipate that
this method will provide future opportunity to convert more of the
resource to the reserve and a pathway to increase mine production
in the future to better utilize the installed mill capacity of
4,400 tonnes per day. We intend to update the mine plan in 2024 to
incorporate these improvement opportunities.
2023 Capital and Exploration Guidance
In 2023, the Company plans to spend a total of $400 million in
sustaining and expansionary capital expenditures at its operating
mines and the Santo Domingo Project. This is broken down into $140
million on sustaining capital and $260 million on expansionary
capital, mainly related to completing the construction of the
Mantoverde Development Project. Pinto Valley sustaining capital
spend relates to investments in infrastructure upgrades that will
increase water reliability and strengthen tailings
stewardship.
Pinto Valley
Mantos Blancos
Manto- verde*
Cozamin
Santo Domingo
Total
Capital Expenditure ($
millions)
Sustaining Capital1
70
20
25
25
-
140
Expansionary Capital1
5
-
225
5
25
260
Total Capital
Expenditures
75
20
250
30
25
400
*Mantoverde shown on a 100% basis
In addition, the Company plans to spend a total of $220 million
in capitalized stripping at its three open pit mines.
Pinto Valley
Mantos Blancos
Mantoverde*
Total
Capitalized Stripping ($
millions)
25
75
120
220
*Mantoverde shown on a 100% basis
A portion of waste material mined at the Mantos Blancos and
Mantoverde mines in 2023 is considered eligible for capitalization
as a stripping asset under Capstone’s accounting policies. In the
Mantoverde and Mantos Blancos technical reports dated November 29,
2021, the costs associated with mining this waste material were
considered to be operating costs. Total mine movement has not
increased compared to the technical reports, only the
classification between operating costs and capitalized
stripping.
Finally, the Company plans to spend $10 million in brownfield
and greenfield exploration activities in 2023. Brownfield
exploration is focused on resource to reserve conversion at
Cozamin, Mantos Blancos and Mantoverde with greenfield exploration
focused mainly on the high-grade Planalto project in
Brazil.
$ millions
Brownfield Exploration
6
Greenfield Exploration
4
Total Exploration
10
2023 Key Catalysts
2023 will be a catalyst-rich year with the following feasibility
studies and milestones expected to be delivered:
- Updated 43-101 Cozamin Mine Plan – Q1 2023
- ESG strategy roll-out – Q1 2023
- PV4 Feasibility Study – H1 2023
- Mantos Blancos Phase II Feasibility Study – H2 2023
- Mantoverde Phase II Feasibility Study – H2 2023
- Updated Santo Domingo Feasibility Study (Copper-Iron) including
MV-SD district synergies – H2 2023
- Commissioning of MVDP – Before year-end 2023
2022 Year-end Results Announcement and Conference
Call
Capstone will release its 2022 Full-year results on Wednesday,
February 15, 2023 prior to market open. Management will host an
investor conference call on Wednesday, February 15, 2023 at 11:00
am ET/8:00 am PT. Details to join the call are as follows:
2022 Year-end Webcast and
Conference Call Details
Conference call webcast
link: https://app.webinar.net/egzVo3NwjOM
To connect by phone:
To instantly join the conference
call by phone, please use the following URL https://bit.ly/3HyQ0d2
to easily register yourself and be connected into the conference
call automatically.
You can also dial direct to be
entered to the call by the operator:
Toronto: (+1) 416-764-8650
Vancouver: (+1) 778-383-7413
North America toll free:
888-664-6383
Confirmation # 73116236
An audio replay of the conference call will be available until
March 1, 2023.
Replay Dial-in Numbers
Toronto: (+1) 416-764-8677
North America toll free:
888-390-0541
Code: 116236#
After the replay expiration, an audio file will be available on
Capstone’s website at Capstone Copper - Events and Presentations.
Further information is available at www.capstonecopper.com
ABOUT CAPSTONE COPPER CORP.
Capstone Copper Corp. is an Americas-focused copper mining
company headquartered in Vancouver, Canada. We own and operate the
Pinto Valley copper mine located in Arizona, USA, the Cozamin
copper-silver mine located in Zacatecas, Mexico, the Mantos Blancos
copper-silver mine located in the Antofagasta region, Chile, and
70% of the Mantoverde copper-gold mine, located in the Atacama
region, Chile. In addition, we own the fully permitted Santo
Domingo copper-gold project, located approximately 30 kilometres
northeast of Mantoverde in the Atacama region, Chile, as well as a
portfolio of exploration properties in the Americas.
Capstone Copper’s strategy is to unlock transformational copper
production growth while executing on cost and operational
improvements through innovation, optimization and safe and
responsible production throughout our portfolio of assets. We focus
on profitability and disciplined capital allocation to surface
stakeholder value. We are committed to creating a positive impact
in the lives of our people and local communities, while delivering
compelling returns to investors by sustainably producing copper to
meet the world’s growing needs.
CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS
This document may contain “forward-looking information” within
the meaning of Canadian securities legislation and “forward-looking
statements” within the meaning of the United States Private
Securities Litigation Reform Act of 1995 (collectively,
“forward-looking statements”). These forward-looking statements are
made as of the date of this document and the Company does not
intend, and does not assume any obligation, to update these
forward-looking statements, except as required under applicable
securities legislation.
Forward-looking statements relate to future events or future
performance and reflect our expectations or beliefs regarding
future events and the impacts of the ongoing and evolving COVID-19
pandemic and the evolving geopolitical environment. Forward-looking
statements include, but are not limited to, statements with respect
to the execution of our future growth projects, our financial
liquidity and development of our projects, the estimation of
Mineral Resources and Mineral Reserves, the success of the
underground paste backfill and tailings filtration projects at
Cozamin, the timing and cost of the construction of the paste
backfill and dry stack tailings plant at Cozamin, the success and
timing of the Mantos Blancos Concentrator Debottlenecking Project,
the timing and cost of the Mantoverde Development Project, the
timing and results of the PV4 study, timing and success of the
Jetti Technology, the successful execution of a port services
agreement with Puerto Abierto S.A., the expected reduction in
capital requirements for the Santo Domingo project, the timing and
success of the Cobalt Study for Santo Domingo, the timing and
results of the integrated plan for Mantoverde - Santo Domingo, the
realization of Mineral Reserve estimates, the timing and amount of
estimated future production, the costs of production and capital
expenditures and reclamation, the budgets for exploration at
Cozamin, Santo Domingo, Pinto Valley, Mantos Blancos, Mantoverde
and other exploration projects, the timing and success of the
Copper Cities project, the success of our mining operations, the
continuing success of mineral exploration, the estimations for
potential quantities and grade of inferred resources and
exploration targets, our ability to fund future exploration
activities, our ability to finance the Santo Domingo project and
other current or future projects and expansions, environmental
risks, unanticipated reclamation expenses and title disputes, the
success of the synergies and catalysts related to the combined
business following the Company’s recent arrangement, and the
anticipated future production, costs of production, including the
cost of sulphuric acid and oil and other fuel, capital expenditures
and reclamation of the Company's operations and development
projects and the risks included in our continuous disclosure
filings on SEDAR at www.sedar.com. The
potential effects of the COVID-19 pandemic on our business and
operations are unknown at this time, including Capstone Copper’s
ability to manage challenges and restrictions arising from COVID-19
in the communities in which Capstone Copper operates and our
ability to continue to safely operate and to safely return our
business to normal operations. The impact of COVID-19 to Capstone
Copper is dependent on a number of factors outside of our control
and knowledge, including the effectiveness of the measures taken by
public health and governmental authorities to combat the spread of
the disease, global economic uncertainties and outlook due to the
disease, supply chain delays resulting in lack of availability of
supplies, goods and equipment, and evolving restrictions relating
to mining activities and to travel in certain jurisdictions in
which we operate.
In certain cases, forward-looking statements can be identified
by the use of words such as “anticipates”, “approximately”,
“believes”, “budget”, “estimates”, “expects”, “forecasts”,
“guidance”, intends”, “plans”, “scheduled”, “target”, or variations
of such words and phrases, or statements that certain actions,
events or results “be achieved”, “could”, “may”, “might”, “occur”,
“should”, “will be taken” or “would” or the negative of these terms
or comparable terminology. In this document certain forward-looking
statements are identified by words including “anticipated”,
“expected”, “guidance” and “plan”. The forward-looking statements
in this document are necessarily based on a number of estimates and
assumptions that, while considered reasonable by the Company as at
the date of such statements, are inherently subject to the
business, economic and competitive uncertainties and contingencies.
The Company has based these forward-looking statements on the
Company’s current expectations and projections about future events.
By their very nature, forward-looking statements involve known and
unknown risks, uncertainties and other factors that may cause our
actual results, performance or achievements to be materially
different from any future results, performance or achievements
expressed or implied by the forward-looking statements. Such
factors include, amongst others, risks related to inherent hazards
associated with mining operations and closure of mining projects,
future prices of copper and other metals, compliance with financial
covenants, surety bonding, our ability to raise capital, Capstone
Copper’s ability to acquire properties for growth, counterparty
risks associated with sales of our metals, use of financial
derivative instruments and associated counterparty risks, foreign
currency exchange rate fluctuations, market access restrictions or
tariffs, changes in general economic conditions, availability and
quality of water, accuracy of Mineral Resource and Mineral Reserve
estimates, operating in foreign jurisdictions with risk of changes
to governmental regulation, compliance with governmental
regulations, compliance with environmental laws and regulations,
reliance on approvals, licences and permits from governmental
authorities and potential legal challenges to permit applications,
contractual risks including but not limited to, our ability to meet
the completion test requirements under the Cozamin Silver Stream
Agreement with Wheaton Precious Metals Corp. ("Wheaton"), our
ability to meet certain closing conditions under the Santo Domingo
Gold Stream Agreement with Wheaton, acting as Indemnitor for Minto
Metals Corp.’s surety bond obligations post divestiture, impact of
climate change and changes to climatic conditions at our operations
and projects, changes in regulatory requirements and policy related
to climate change and greenhouse gas ("GHG") emissions, land
reclamation and mine closure obligations, aboriginal title claims
and rights to consultation and accommodation, risks relating to
widespread epidemics or pandemic outbreak including the COVID-19
pandemic; the impact of COVID-19 on our workforce, risks related to
construction activities at our operations and development projects,
suppliers and other essential resources and what effect those
impacts, if they occur, would have on our business, including our
ability to access goods and supplies, the ability to transport our
products and impacts on employee productivity, the risks in
connection with the operations, cash flow and results of Capstone
Copper relating to the unknown duration and impact of the COVID-19
pandemic, impacts of geopolitical events and the effects of global
supply chain disruptions, uncertainties and risks related to the
potential development of the Santo Domingo project, risks related
to the Mantos Blancos Concentrator Debottlenecking Project and the
Mantoverde Development Project, increased operating and capital
costs, increased cost of reclamation, challenges to title to our
mineral properties, increased taxes in jurisdictions the Company
operates or is subject to tax, changes in tax regimes we are
subject to and any changes in law or interpretation of law may be
difficult to react to in an efficient manner, maintaining ongoing
social licence to operate, seismicity and its effects on our
operations and communities in which we operate, dependence on key
management personnel, potential conflicts of interest involving our
directors and officers, corruption and bribery, limitations
inherent in our insurance coverage, labour relations, increasing
input costs such as those related to sulphuric acid, electricity,
fuel and supplies, increasing inflation rates, competition in the
mining industry including but not limited to competition for
skilled labour, risks associated with joint venture partners and
non-controlling shareholders or associates, our ability to
integrate new acquisitions and new technology into our operations,
cybersecurity threats, legal proceedings, the volatility of the
price of the Common Shares, the uncertainty of maintaining a liquid
trading market for the Common Shares, risks related to dilution to
existing shareholders if stock options or other convertible
securities are exercised, the history of Capstone Copper with
respect to not paying dividends and anticipation of not paying
dividends in the foreseeable future and sales of Common Shares by
existing shareholders can reduce trading prices, and other risks of
the mining industry as well as those factors detailed from time to
time in the Company’s interim and annual financial statements and
MD&A of those statements, all of which are filed and available
for review under the Company’s profile on SEDAR at www.sedar.com. Although the Company has attempted
to identify important factors that could cause our actual results,
performance or achievements to differ materially from those
described in our forward-looking statements, there may be other
factors that cause our results, performance or achievements not to
be as anticipated, estimated or intended. There can be no assurance
that our forward-looking statements will prove to be accurate, as
our actual results, performance or achievements could differ
materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on our forward-looking
statements.
CAUTIONARY NOTE TO UNITED STATES INVESTORS REGARDING
PRESENTATION OF MINERAL RESERVE AND MINERAL RESOURCE
ESTIMATES
As a British Columbia corporation and a “reporting issuer” under
Canadian securities laws, we are required to provide disclosure
regarding our mineral properties in accordance with Canadian
National Instrument 43-101 – Standards of Disclosure for Mineral
Projects (“NI 43-101”). NI 43-101 is a rule developed by the
Canadian Securities Administrators that establishes standards for
all public disclosure an issuer makes of scientific and technical
information concerning mineral projects. In accordance with NI
43-101, we use the terms mineral reserves and resources as they are
defined in accordance with the CIM Definition Standards on mineral
reserves and resources (the “CIM Definition Standards”) adopted by
the Canadian Institute of Mining, Metallurgy and Petroleum. In
particular, the terms “mineral reserve”, “proven mineral reserve”,
“probable mineral reserve”, “mineral resource”, “measured mineral
resource”, “indicated mineral resource” and “inferred mineral
resource” used in this annual information form and the documents
incorporated by reference herein and therein, are Canadian mining
terms defined in accordance with CIM Definition Standards. These
definitions differ from the definitions in the disclosure
requirements promulgated by the SEC. Accordingly, information
contained in this annual information form and the documents
incorporated by reference herein may not be comparable to similar
information made public by U.S. companies reporting pursuant to SEC
disclosure requirements.
United States investors are also cautioned that while the SEC
will now recognize “measured mineral resources”, “indicated mineral
resources” and “inferred mineral resources”, investors should not
assume that any part or all of the mineralization in these
categories will ever be converted into a higher category of mineral
resources or into mineral reserves. Mineralization described using
these terms has a greater amount of uncertainty as to their
existence and feasibility than mineralization that has been
characterized as reserves. Accordingly, investors are cautioned not
to assume that any “measured mineral resources”, “indicated mineral
resources”, or “inferred mineral resources” that we report are or
will be economically or legally mineable. Further, “inferred
resources” have a greater amount of uncertainty as to their
existence and as to whether they can be mined legally or
economically. Therefore, United States investors are also cautioned
not to assume that all or any part of the inferred resources exist.
In accordance with Canadian rules, estimates of “inferred mineral
resources” cannot form the basis of feasibility or other economic
studies, except in limited circumstances where permitted under NI
43-101.
COMPLIANCE WITH NI 43-101
Unless otherwise indicated, Capstone has prepared the technical
information in this document (“Technical Information”) based on
information contained in the technical reports, news releases and
other public filings (collectively the “Disclosure Documents”)
available under Capstone Copper Corp.’s company profile on SEDAR at
www.sedar.com. Each Disclosure Document was prepared by or under
the supervision of a qualified person (a “Qualified Person”) as
defined in National Instrument 43-101. For readers to fully
understand the information in this document, readers are encouraged
to review the full text of the Disclosure Documents, including the
qualifications, assumptions and exclusions that relate to the
Technical Information set out in this document, which qualifies the
Technical Information. Readers are advised that Mineral Resources
that are not Mineral Reserves do not have demonstrated economic
viability. The Disclosure Documents are each intended to be read as
a whole, and sections should not be read or relied upon out of
context. The Technical Information is subject to the assumptions
and qualifications contained in the Disclosure Documents.
Disclosure Documents include the National Instrument 43-101
compliant technical reports titled “Santo Domingo Project, Region
III, Chile, NI 43-101 Technical Report” effective February 19, 2020
and “Mantoverde and Mantoverde Development Project, NI 43-101
Technical Report, Chañaral / Región de Atacama, Chile” effective
November 29, 2021.
The disclosure of Scientific and Technical Information in this
document was reviewed and approved by Cashel Meagher, P.Geo.,
President and Chief Operating Officer and Peter Amelunxen, PE, VP
Technical Services (technical information related to project
updates at Santo Domingo and Mineral Reserves and Resources at
Mantos Blancos and Mantoverde), all Qualified Persons under NI
43-101.
ALTERNATIVE PERFORMANCE MEASURES
This document refers to certain non-GAAP financial performance
measures, including “C1 cash cost”, “cash cost”, “EBITDA”,
“adjusted EBITDA”, “operating cash flow before changes in working
capital”, “adjusted net (loss) income”, “net debt”, “net cash”,
“all-in sustaining costs”, “all-in costs”, “available liquidity”,
“expansionary capital” and “sustaining capital” are Alternative
Performance Measures. Alternative performance measures are
furnished to provide additional information. These non-GAAP
performance measures are included in this presentation because
these statistics are key performance measures that management uses
internally to monitor performance, to assess how the Company is
performing, to plan and to assess the overall effectiveness and
efficiency of mining operations. These performance measures do not
have a standard meaning within IFRS and, therefore, amounts
presented may not be comparable to similar data presented by other
mining companies. These performance measures should not be
considered in isolation as a substitute for measures of performance
in accordance with IFRS. For full information, please refer to the
Company’s latest Management Discussion and Analysis published on
its Financial Reporting webpage or on SEDAR (the “MD&A”)
C1 Cash Cost per pound: C1 cash costs per payable pound
of copper produced is a measure reflective of operating costs per
unit. C1 cash costs is calculated as cash production costs of metal
produced net of by-product credits and is a key performance measure
that management uses to monitor performance. Management uses this
measure to assess how well the Company’s producing mines are
performing and to assess overall efficiency and effectiveness of
the mining operations and assumes that realized by-product prices
are consistent with those prevailing during the reporting
period.
EBITDA: EBITDA is net income before net finance expense,
tax expense, and depletion and amortization.
Adjusted EBITDA: Adjusted EBITDA is EBITDA before the
pre-tax effect of the adjustments made to adjusted net (loss)
income (above) as well as certain other adjustments required under
the RCF agreement in the determination of EBITDA for covenant
calculation purposes. The adjustments made to Adjusted net (loss)
income and Adjusted EBITDA allow management and readers to analyze
our results more clearly and understand the cash generating
potential of the Company.
Operating cash flow before change in working capital:
Operating Cash Flow before changes in working capital per common
share is a performance measure used by the Company to assess its
ability to generate cash from its operations, while also taking
into consideration changes in the number of outstanding shares of
the Company.
Adjusted net (loss) income: Adjusted net (loss) income is
net income as reported, adjusted for certain types of transactions
that in our judgment are not indicative of our normal operating
activities or do not necessarily occur on a regular basis.
Net debt / net cash: Net debt / Net cash is a performance
measure used by the Company to assess its financial position and is
composed of Long-term debt (excluding deferred financing costs and
purchase price accounting ("PPA") fair value adjustments), due to
related parties, cash and cash equivalents and short-term
investments.
All-in sustaining costs: All-in sustaining costs per
payable pound of copper produced is an extension of the C1 cash
costs measure discussed above and is also a key performance measure
that management uses to monitor performance. Management uses this
measure to analyze margins achieved on existing assets while
sustaining and maintaining production at current levels.
Consolidated All-in sustaining costs includes sustaining capital
and corporate general and administrative costs.
_____________________
1 These are alternative performance
measures. Refer to the section entitled Alternative Performance
Measures in the Cautionary Notes
2 2022 C1 Cash Costs are preliminary.
Final results will be released on February 15th, 2023.
View source
version on businesswire.com: https://www.businesswire.com/news/home/20230201005349/en/
Jerrold Annett, SVP, Strategy and Capital Markets 647-273-7351
jannett@capstonecopper.com
Kettina Cordero, Director Investor Relations &
Communications 604-262-9794 kcordero@capstonecopper.com
Credit Suisse (NYSE:CS)
Historical Stock Chart
From Mar 2023 to Mar 2023
Credit Suisse (NYSE:CS)
Historical Stock Chart
From Mar 2022 to Mar 2023