Iris Energy Limited (NASDAQ: IREN) ("Iris Energy" or "the
Company"), a leading owner and operator of institutional-grade,
highly efficient proprietary Bitcoin mining data centers powered by
100% renewable energy, today published a monthly investor update
for December 2022, containing its results from operations as well
as business updates.
Key Highlights1
Key metrics2 |
Dec-22 |
Average operating hashrate (PH/s) |
1,086 |
Bitcoin mined |
123 |
Mining revenue (US$’000) |
2,089 |
Electricity costs (US$’000) |
1,505 |
Revenue per Bitcoin (US$) |
16,999 |
Electricity costs per Bitcoin (US$) |
12,244 (9,593 adj)3 |
- Corporate:
- 2.0 EH/s of total
miner capacity installed, in-transit or pending deployment
- Following month
end, ~0.4 EH/s of S19j Pro miners was installed, increasing total
Company operating capacity by >30% to 1.5 EH/s4
- 160MW of data center capacity in BC not
affected by recent BC Government decision to temporarily suspend
new and early stage connection requests for cryptocurrency
mining
- Liquidity position and initiatives (as
of calendar year end):
- $39 million cash,
no debt5
- Repayment by
Non-Recourse SPV 1 of all outstanding amounts (approximately $1
million) under the SPV 1 Financing Agreement
- Following month
end, ~$6 million in net cash proceeds received from further
monetization of Bitmain prepayments
- Operations (for the
month of December 2022):
- Average operating
hashrate of 1,086 PH/s (-25% vs. November)
- Monthly operating
revenue of US$2.1 million (-27% vs. November)
- 123 Bitcoin mined
(-19% vs. November)
The reduction in operating metrics (vs.
November) primarily reflects the first full month of operations
following termination of hosting arrangements in connection with
certain of the Group’s limited recourse equipment financing
facilities following receipt of an acceleration notice from the
relevant lender under such
facilities6
- Construction:
- Mackenzie (80MW –
BC, Canada)
- Expansion from 50MW
to 80MW energized on December 6, 2022, three weeks ahead of
schedule
- Childress (20MW –
Texas, USA)
- Civil works for the
substation and first data center building (20MW) complete
- First data center building (20MW)
structure complete, transformers installed, switchgear installed,
cladding and miner racking installation ongoing
- Arrival of the 600MW transformer
(345kV) and two 100MW transformers (138kV)
Corporate update
2.0 EH/s of total miner capacity, operating
capacity increased by >30% to 1.5 EH/s
During the month, the Company transported S19j
Pro miners from Texas, US to BC, Canada for installation at
Mackenzie. The Company has installed approximately 0.4 EH/s of the
miners as of January 8, 2023, increasing total Company operating
capacity by >30% to 1.5 EH/s4. The Group has total miner
capacity of 2.0 EH/s installed, in-transit or pending
deployment.
160MW of data center capacity in BC not affected
by recent BC Government announcements
On December 23, 2022, the Company announced that
its 160MW of data center capacity in BC is not affected by the
recent announcement by the Government of British Columbia to
temporarily suspend new and early-stage BC Hydro connection
requests from cryptocurrency mining projects due to unprecedented
interest7. According to the release, cryptocurrency mining projects
that are operational, and a small number of projects that are well
advanced in BC Hydro’s connection process, will not be
affected.
BC Hydro has confirmed directly with the Company
that its 160MW of data center capacity at Canal Flats (30MW),
Prince George (50MW) and Mackenzie (80MW) is unaffected.
The update can be accessed via the following
link:
https://irisenergy.gcs-web.com/news-releases/news-release-details/iris-energys-160mw-data-center-capacity-british-columbia-not
Liquidity position and initiatives
As at 2022 calendar year end, the Group has $39
million of cash in the bank (preliminary and unaudited) and no
debt5.
On December 21, 2022, Non-Recourse SPV 1 repaid
all outstanding amounts (approximately $1 million) under the SPV 1
Financing Agreement.
In respect of the outstanding limited recourse
equipment financing facilities held by Non-Recourse SPV 2 and
Non-Recourse SPV 3, there have been no further updates since the
Company’s announcements on November 7, 2022 and November 21,
2022.
In January 2023, the Group also monetized an
additional portion of its prepayments with Bitmain by purchasing
and then on-selling miners to a third party, which has resulted in
net cash proceeds of approximately $6 million. As a result,
unutilized prepayments made to Bitmain reduced to approximately $67
million (from $75 million) which relate to an additional ~6.7 EH/s
of S19j Pro miners8, which is separate and incremental to the
Group's previously announced 2.0 EH/s of capacity.
Growth strategy
The Company continues to take a risk-focused
approach to weather the storm and capitalize on the next bull
run:
-
Continued exploration of strategic options to monetize assets,
including approximately $67 million of prepayments already made to
Bitmain with respect to an additional ~6.7 EH/s of miners
- Strategic focus
remains on expanding our self-mining capacity
-
In parallel, assessment of opportunities to utilize available data
center capacity in the near-to-medium term via potential
third-party hosting, recognizing the scarcity of industry hosting
data center capacity in the current market
See the Company’s latest investor presentation for further
details: https://investors.irisenergy.co/events-and-presentations
Legal proceedings
The Company is aware that on December 14, 2022, a putative
securities class action complaint naming the Company and certain of
its directors and officers was filed in the U.S. District Court for
the District of New Jersey. The filed complaint asserts claims
under Section 10(b) and 20(a) of the Securities Exchange Act of
1934 and Sections 11 and 15 of the Securities Act of 1933,
contending that certain of the Company's statements, including with
respect to its equipment financing arrangements, were allegedly
false or misleading. The Company believes these claims are without
merit and intends to defend itself vigorously.
Canal Flats update (0.8 EH/s, 30MW
capacity) – BC, Canada
Canal Flats has been powered by 100% renewable
energy since inception9.
The project achieved average monthly operating
hashrate of 510 PH/s in December compared to 570 PH/s last
month.
Mackenzie update (2.5 EH/s, 80MW
capacity) – BC, Canada
Mackenzie has been powered by 100% renewable
energy since inception9.
The project achieved average monthly operating
hashrate of 184 PH/s in December compared to 268 PH/s last
month.
On December 6, 2022, the 30MW expansion of
capacity at Mackenzie (from 50MW to 80MW) was energized ahead of
schedule. The expansion includes a newly constructed 20MW data
center building as well as utilizing 10MW of an existing data
center building.
Prince George update (1.4 EH/s, 50MW
capacity) – BC, Canada
Prince George has been powered by 100% renewable
energy since inception9.
The project achieved average monthly operating
hashrate of 393 PH/s in December compared to 607 PH/s last
month.
Childress update (0.7 EH/s, 20MW
capacity) – Texas, USA
All civil works for the substation and first
data center building are complete. The first data center building
(20MW) structure is complete, with exterior cladding installation
ongoing. The data center transformers and switchgear have been
delivered and installed, with the internal fit out of miner racking
ongoing.
The 600MW transformer (345kV) and two 100MW
transformers (138kV) have been delivered to site with assembly
ongoing.
Community engagement
In December 2022, Iris Energy team members
wrapped Christmas presents in Childress with two of our grant
recipients: (i) the Childress Women’s League, who provide groceries
to families of school children who need support; and (ii) Childress
County Sharing, who provide Christmas gifts to the elderly, the
disabled and families in need.
Future development sites
Development works continued across additional
sites in Canada, the USA and Asia-Pacific, which have the potential
to support up to an additional >1GW of aggregate power capacity
capable of powering growth beyond the Company’s 760MW of announced
power capacity.
Operating and financial results
Daily average operating hashrate chart is available
at https://www.globenewswire.com/NewsRoom/AttachmentNg/b89bdfc5-d064-48bb-961c-46de8c782ee1
Technical commentary
The Company’s average operating hashrate was
1,086 PH/s in December (compared to 1,445 PH/s in November), with
the decrease reflecting the first full month of operations
following termination of hosting arrangements in connection with
certain of the Group’s limited recourse equipment financing
facilities following receipt of an acceleration notice from the
relevant lender under such facilities. The corresponding decrease
in Bitcoin mined (123 vs. 151 in November) and electricity costs
($1.5 million vs. $1.9 million in November) were also primarily
attributable to the termination of these hosting arrangements.
Adjusted electricity costs per Bitcoin was $9.6k in December
(compared to $10.2k in November), with the decrease primarily
attributable to a decrease in the difficulty-implied global
hashrate during the period3.
Operating |
Oct-22 |
Nov-22 |
Dec-22 |
Renewable energy usage
(MW)10 |
123 |
46 |
35 |
Avg operating hashrate (PH/s) |
3,899 |
1,445 |
1,086 |
Financial (unaudited)2 |
Oct-22 |
Nov-22 |
Dec-22 |
Bitcoin mined |
448 |
151 |
123 |
Mining revenue (US$’000) |
8,785 |
2,871 |
2,089 |
Electricity costs (US$’000) |
4,167 |
1,905 |
1,505 |
Revenue per Bitcoin (US$) |
19,591 |
18,955 |
16,999 |
Electricity costs per Bitcoin (US$) |
9,293 |
12,581 (10,168 adj)3 |
12,244 (9,593 adj)3 |
Miner Shipping Schedule* |
Hardware |
Units |
EH/s (incremental) |
EH/s(cumulative) |
Operating (as of January 8) |
S19j Pro11 |
14,547 |
1.5 |
1.5 |
Inventory – pending deployment or in transit |
S19j Pro12 |
6,717 |
0.5 |
2.0 |
Total |
|
21,264 |
2.0 |
2.0 |
* Excludes ~3.6 EH/s of miners securing
equipment financing facilities with the Company’s two remaining SPV
borrowers in respect of which the Company has received a notice of
acceleration from the relevant lender, none of which have been
operating following termination of relevant hosting arrangements as
described above. See the Company's Report on Form 6-K filed on
November 21, 2022 for further information.
Site |
Capacity (MW) |
Capacity (EH/s)13 |
Timing |
Status |
Canal Flats (BC, Canada) |
30 |
0.8 |
Complete |
Operating |
Mackenzie (BC, Canada) |
50 |
1.5 |
Complete |
Operating |
30 |
1.0 |
Complete |
Energized |
Prince George (BC, Canada) |
50 |
1.4 |
Complete |
Operating |
Total (BC, Canada) |
160 |
4.7 |
|
|
Childress (Texas, US) |
20 |
0.7 |
2023 |
Under construction14 |
Total (Canada & USA) |
180 |
5.4 |
|
|
About Iris Energy
Iris Energy is a sustainable Bitcoin mining
company that supports the decarbonization of energy markets and the
global Bitcoin network.
- 100% renewables:
Iris Energy targets markets with low-cost, under-utilized renewable
energy, and where the Company can support local communities
- Long-term security
over infrastructure, land and power supply: Iris Energy builds,
owns and operates its electrical infrastructure and proprietary
data centers, providing long-term security and operational control
over its assets
- Seasoned management
team: Iris Energy’s team has an impressive track record of success
across energy, infrastructure, renewables, finance, digital assets
and data centers with cumulative experience in delivering >$25bn
in energy and infrastructure projects globally
Forward-Looking Statements
This investor update includes “forward-looking
statements” within the meaning of the Private Securities Litigation
Reform Act of 1995. Forward-looking statements generally relate to
future events or Iris Energy’s future financial or operating
performance. For example, forward-looking statements include but
are not limited to, the Company’s expected power capacity and
operating capacity, and the impact of an event of default and/or
acceleration of amounts due under limited recourse equipment
financing arrangements in the Company’s special purpose vehicles.
In some cases, you can identify forward-looking statements by
terminology such as “anticipate,” “believe,” “may,” “can,”
“should,” “could,” “might,” “plan,” “possible, ”project,” “strive,”
“budget,” “forecast,” “expect,” “intend,” “target”, “will,”
“estimate,” “predict,” “potential,” “continue”, ”scheduled” or the
negatives of these terms or variations of them or similar
terminology, but the absence of these words does not mean that
statement is not forward-looking. Such forward-looking statements
are subject to risks, uncertainties, and other factors which could
cause actual results to differ materially from those expressed or
implied by such forward looking statements. In addition, any
statements or information that refer to expectations, beliefs,
plans, projections, objectives, performance or other
characterizations of future events or circumstances, including any
underlying assumptions, are forward-looking.
These forward-looking statements are based on
management’s current expectations and beliefs. These statements are
neither promises nor guarantees, but involve known and unknown
risks, uncertainties and other important factors that may cause
Iris Energy’s actual results, performance or achievements to be
materially different from any future results, performance or
achievements expressed or implied by the forward-looking
statements, including, but not limited to: Iris Energy’s limited
operating history with operating losses; electricity outage,
limitation of electricity supply or increase in electricity costs;
long term outage or limitation of the internet connection at Iris
Energy’s sites; any critical failure of key electrical or data
center equipment; serial defects or underperformance with respect
to Iris Energy’s equipment; failure of suppliers to perform under
the relevant supply contracts for equipment that has already been
procured which may delay Iris Energy’s expansion plans; supply
chain and logistics issues for Iris Energy or Iris Energy’s
suppliers; cancellation or withdrawal of required operating and
other permits and licenses; customary risks in developing
greenfield infrastructure projects; Iris Energy’s evolving business
model and strategy; Iris Energy’s ability to successfully manage
its growth; Iris Energy’s ability to raise additional financing
(whether because of the conditions of the markets, Iris Energy’s
financial condition or otherwise) on a timely basis, or at all,
which could adversely impact the Company’s ability to meet its
capital commitments (including payments due under its hardware
purchase contracts with Bitmain) and the Company’s growth plans;
Iris Energy’s failure to make certain payments due under any one of
its hardware purchase contracts with Bitmain on a timely basis
could result in liquidated damages, claims for specific performance
or other claims against Iris Energy, any of which could result in a
loss of all or a portion of any prepayments or deposits made under
the relevant contract or other liabilities in respect of the
relevant contract, and could also result in Iris Energy not
receiving certain discounts under the relevant contract or
receiving the relevant hardware at all, any of which could
adversely impact its business, operating expansion plans, financial
condition, cash flows and results of operations; the failure of
Iris Energy’s wholly-owned special purpose vehicles to make
required payments of principal and/or interest under their limited
recourse equipment financing arrangements when due or otherwise
comply with the terms thereof, as a result of which the lender
thereunder has declared the entire principal amount of each loan to
be immediately due and payable, and while no assurance can be
provided as to what actions may be taken, we expect such lender
will take steps to enforce the indebtedness and its rights in the
Bitcoin miners with respect to certain of such loans (and
potentially all such loans) and other assets securing such loans,
which would result in the loss of the relevant Bitcoin miners
securing such loans and materially reduce the Company’s operating
capacity, and could also lead to bankruptcy or liquidation of the
relevant special purpose vehicles, and materially and adversely
impact the Company’s business, operating expansion plans, financial
condition, cash flows and results of operations; the terms of any
additional financing or any refinancing, restructuring or
modification to the terms of any existing financing, which could be
less favorable or require Iris Energy to comply with more onerous
covenants or restrictions, any of which could restrict its business
operations and adversely impact its financial condition, cash flows
and results of operations; competition; Bitcoin prices, global
hashrate and the market value of Bitcoin miners, any of which could
adversely impact the Company’s financial condition, cashflows and
results of operations, as well as its ability to raise additional
financing and the ability of its wholly-owned special purpose
vehicles to make required payments of principal and/or interest on
their equipment financing facilities; risks related to health
pandemics including those of COVID-19; changes in regulation of
digital assets; and other important factors discussed under the
caption “Risk Factors” in Iris Energy’s Annual Report on Form 20-F
for the fiscal year ended June 30, 2022 filed with the
SEC on September 13, 2022, as such factors may be updated from time
to time in its other filings with the SEC, accessible on the SEC’s
website at www.sec.gov and the Investor Relations section of Iris
Energy’s website at https://investors.irisenergy.co.
These and other important factors could cause
actual results to differ materially from those indicated by the
forward-looking statements made in this investor update. Any
forward-looking statement that Iris Energy makes in this investor
update speaks only as of the date of such statement. Except as
required by law, Iris Energy disclaims any obligation to update or
revise, or to publicly announce any update or revision to, any of
the forward-looking statements, whether as a result of new
information, future events or otherwise.
Preliminary Financial
Information
The preliminary financial information for the
month of December 2022 included in this investor update is not
subject to the same closing procedures as our unaudited quarterly
financial results and has not been reviewed by our independent
registered public accounting firm. The preliminary financial
information included in this investor update does not represent a
comprehensive statement of our financial results or financial
position and should not be viewed as a substitute for unaudited
financial statements prepared in accordance with International
Financial Reporting Standards. Accordingly, you should not place
undue reliance on the preliminary financial information included in
this investor update.Contacts
MediaJon SnowballDomestique+61 477 946 068
InvestorsLincoln TanIris Energy+61 407 423
395lincoln.tan@irisenergy.co
To keep updated on Iris Energy’s news releases and SEC filings,
please subscribe to email alerts at
https://investors.irisenergy.co/ir-resources/email-alerts.
___________________________1 All timing references in this
investor update are to calendar quarters and calendar years, in
each case unless otherwise specified.2 Bitcoin and Bitcoin mined in
this investor update are presented in accordance with our revenue
recognition policy which is determined on a Bitcoin received basis
(post deduction of mining pool fees as applicable).3 The Company’s
unadjusted electricity costs per Bitcoin mined are currently
elevated primarily due to excess demand charges attributable to
average unutilized power capacity (due to termination of hosting
arrangements in connection with certain of the Group’s limited
recourse equipment financing facilities). The adjusted electricity
costs per Bitcoin mined excludes such excess demand charges (i.e.
assumes unit electricity costs of ~$0.045/kWh).4 As of January 8,
2023, compared to operating capacity of approximately 1.1 EH/s as
of December 12, 2022 (per November 2022 investor update). Reflects
operating capacity following the termination of hosting
arrangements during the month of November in connection with the
Group’s two outstanding limited recourse equipment financing
facilities following receipt of an acceleration notice from the
relevant lender under such facilities. Refer to the Company’s
announcements on November 7, 2022 and November 21, 2022.5 Reflects
USD equivalent, unaudited preliminary cash balance as of December
31, 2022 (excluding cash held by the two remaining SPV borrowers).
Reflects acceleration of outstanding loans under the Group's two
outstanding limited recourse equipment financing facilities and
assumes foreclosure by the lender thereunder against the collateral
securing such facilities held by such non-recourse SPV borrowers.
See the Company's Report on Form 6-K filed on November 21, 2022 and
Registration Statement on Form F-1/A filed on December 21, 2022 for
further information. Following such acceleration and foreclosure,
the Group would not have any indebtedness for borrowed money
outstanding.6 Refer to the Company’s announcements on November 7,
2022 and November 21, 2022.7 See December 21, 2022 press release
from the British Columbia Ministry of Energy, Mines and Low Carbon
Innovation titled “Province hits pause on electrical connections
for cryptocurrency mining”.8 Excludes any discount arrangements
under the relevant agreement, which may include potential
additional miners. The timing and volume of any additional future
deliveries under the separate $400 million hardware purchase
contract for miners are subject to ongoing discussions with
Bitmain. The Company has not made all recent payments under that
contract and does not currently expect to make upcoming payments in
respect of any such additional future deliveries under that
contract. The Company can make no assurances as to the outcome of
these discussions (including any impact on the Company’s expansion
plans or payments made under that contract or whether the $67m of
prepayments will be able to used against future hardware purchases
(in whole or in part)). See further detail in the Company’s
previous announcements dated June 21, 2022, August 1, 2022 and
November 2, 2022.9 Currently approximately 97% directly from
renewable energy sources; approximately 3% from purchase of RECs.10
Comprises actual power usage for Canal Flats, Mackenzie and Prince
George.11 Includes mix of lower efficiency hardware, which is
estimated to represent less than 6% of the operating 1.5 EH/s.12
Includes mix of lower efficiency hardware, which is estimated to
represent less than 10% of miners in transit and/or pending
deployment.13 Reflects estimated hashrate capacity by site assuming
full utilization of available data center capacity with additional
Bitmain S19j Pro miners.14 Decisions around how much, and when,
data center capacity above an initial 20MW will be built at
Childress are being assessed.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/bbbc0733-e802-4be6-a77d-2989b27e66d5
https://www.globenewswire.com/NewsRoom/AttachmentNg/7b4a125d-9f0e-4c9d-a91c-eeb5d79055ff
https://www.globenewswire.com/NewsRoom/AttachmentNg/a14ffc9c-d086-41e6-8088-299ee4f34c78
https://www.globenewswire.com/NewsRoom/AttachmentNg/9be9d8dd-22a6-4392-92fb-bf2ca39ef82e
Iris Energy (NASDAQ:IREN)
Historical Stock Chart
From May 2023 to Jun 2023
Iris Energy (NASDAQ:IREN)
Historical Stock Chart
From Jun 2022 to Jun 2023