Bitdeer Technologies Group (NASDAQ: BTDR)
(“
Bitdeer” or the “
Company”), a
world-leading technology company for blockchain and
high-performance computing, today announced its unaudited mining
and operations updates for August 2024.
Operational Update
- Self-mined Bitcoin: Mined 166 Bitcoins.
- Hosting:
- Client hosted mining machines decreased by 45,000 units in
August due to the transition of hosting customers and Texas 100 MW
hydro-cooling conversion. The released capacity will be steadily
refilled with new customers’ miners as well as Bitdeer’s SEALMINERs
for self-mining from Sep 2024 to Q1 2025.
- Mining Rigs Manufacturing and R&D:
- SEALMINER A1 mass production remains on track to be completed
in Q4 2024 and is anticipated to contribute 3.4 EH/s to the
Company’s proprietary hashrate. The deployment of these SEALMINER
A1 rigs is expected to happen concurrently with the energization of
the Texas hydro-cooling conversion and Tydal, Norway phase 1 in Q4
2024 and Q1 2025.
- TSMC’s delivery of SEAL02 initial tape-out wafers remains on
track to be completed by mid-September 2024. Chip verification and
prototype testing will start immediately following tape-out. If
testing is successful, mass production is scheduled to commence
near the end of 2024.
- R&D of SEAL03, our third-generation chip, is ongoing.
- HPC/AI:
- Bitdeer AI cloud services powered by NVIDIA GDX SuperPod with
H100 systems remained near 100% average utilization for this
month.
- TLM Group’s comprehensive research and analysis of Bitdeer’s
global energy assets and datacenter sites remains ongoing.
- Mining Datacenters:
- Construction of the Tydal, Norway, phase 1 site 40 MW
expansions remains on track to be energized in Q4 2024.
- Rockdale, Texas, U.S.A., 100 MW hydro-cooling conversion site
is planned for phased completion between December 2024 and February
2025.
- Jigmeling, Bhutan, 500 MW construction remains on track with
the primary substation expected to be completed by Q1 2025.
- Financing:
- The offering of US$172.5 million aggregate principal amount of
8.50% convertible senior notes due 2029 (the “Convertible Notes”)
was successfully completed in August 2024, including US$22.5
million aggregate principal amount of Convertible Notes pursuant to
the exercise in full by the underwriters in that offering of their
over-allotment option to purchase additional Convertible Notes. The
Company intends to use the net proceeds from the offering of the
Convertible Notes for datacenter expansion, ASIC based mining rig
development as well as working capital and other general corporate
purposes.
- The Company made a partial repayment of the outstanding
principal balance of the senior secured notes issued to sellers in
the Company’s previously announced acquisition of TROLL HOUSING AS
and TYDAL DATA CENTER AS in August 2024 in the amount of US$5
million.
Management Commentary
Linghui Kong, Chief Business Officer of Bitdeer stated, “Further
vertical integration and entry into the growing ASICs market with
our proprietary chip technology are key to Bitdeer’s strategy. In
September, we are set to receive the initial SEAL02 tape-out wafers
from TSMC and we will begin verification and prototype testing.
Upon successful results, mass production is scheduled to commence
near the end of 2024.”
Mr. Kong continued, “In August, Bitcoin mined decreased to 166
Bitcoins as a result of higher network difficulty, temporary
storm-related power disruption at our Tennessee facility and
curtailments at our Rockdale, Texas site due to high summer
heat.”
Production and Operations Summary
Metrics |
August 2024 |
July 2024 |
August 2023 |
Total hash rate under
management1(EH/s) |
16.8 |
21.2 |
21.3 |
- Proprietary hash rate |
8.6 |
8.6 |
8.7 |
• Self-mining |
7.8 |
7.5 |
7.2 |
• Cloud Hash Rate |
0.8 |
1.1 |
1.5 |
- Hosting |
8.2 |
12.6 |
12.6 |
Mining machines under management |
167,000 |
212,000 |
221,000 |
- Self-owned2 |
87,000 |
87,000 |
92,000 |
- Hosted |
80,000 |
125,000 |
129,000 |
Bitcoin mined (self-mining only) |
166 |
181 |
383 |
1 Total hash rate under management as of August
31, 2024 across the Company’s three primary business lines:
Self-mining, Cloud Hash Rate, and Hosting.
- Self-mining refers to cryptocurrency mining
for the Company’s own account, which allows it to directly capture
the high appreciation potential of cryptocurrency.
- Cloud Hash Rate offers hash rate subscription
plans and shares mining income with customers under certain
arrangements. The Cloud Hash Rate stated above reflects the
contracted hash rate with customers at month-end. However,
throughout the month, the Cloud Hash Rate may transition to
Self-mining hash rate if customers opt to not make their monthly
electricity payments for various reasons.
- Hosting encompasses a one-stop mining machine
hosting solution including deployment, maintenance, and management
services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the
Company’s self-mining business and Cloud Hash Rate business.
Infrastructure Construction Update
Rockdale, Texas - Hydro-cooling
conversionRockdale, Texas 100 MW hydro-cooling conversion
key milestones achieved:
- Demolition work started on August 1, 2024. Expected to be
completed by the end of September.
- Cooling system design completed and waiting to begin
construction.
- Equipment procurement is ongoing.
- Water Tower testing have been finished in August and met the
expectation.
- Energization timeline to occur in phases between Q4 2024 and Q1
2025.
Tydal, NorwayTydal, Norway 175 MW site
expansion is progressing well, with several key milestones
achieved:
- Buildings and groundwork have been completed, along with the
construction of the transformer foundation and housing.
- Orders for the procurement of the transformer and electrical
equipment have been placed, with delivery and installation
currently in progress. Additionally, the procurement and delivery
of containers and hydro-cooling systems are underway, and the
construction of drainage systems is ongoing.
- Construction of the substation is ongoing and expected to be
completed by the end of October 2024.
- Tydal, Norway Expansion Phase 1 of 40 MW remains on track to be
energized Q4 2024.
Massillon, OhioMassillon, Ohio 221 MW site is
also making progress:
- Substation conceptual design is completed and long lead-time
electrical equipment for the substation has been ordered.
- Engineering, Procurement, and Construction (EPC) contractor has
been selected for the substation construction.
- Civil work is ongoing, with the majority expected to be
completed by the end of Q4 2024 or Q1 2025.
- Building design is completed, and construction is anticipated
to begin in Q1 2025.
- Estimated energization timeline remains on track for
mid-to-late 2025.
Jigmeling, BhutanJigmeling, Bhutan 500MW site
is progressing well, with the following key milestones
achieved:
- Civil work is nearly completed with an anticipated completion
date by the end of September 2024. Construction of transformer and
container foundations is in progress and will be completed in
phases, with the last phase expected by the end of February
2025.
- 132kv/140MW substation design is completed, 220kv/360MW
substation design is in progress.
- Construction of the substations is anticipated to be ready by
the end of Q1 2025.
- Orders for the procurement of transformers and electrical
equipment have been placed, with delivery and installation to be
completed in phases over the next two quarters.
- Procurement and delivery of containers and hydro-cooling
systems are in progress, with completion in phases by the end of Q1
2025.
Power Infrastructure Summary
Site / Location |
Capacity (MW) |
Status |
Timing3 |
Electrical capacity |
|
|
|
- Rockdale, Texas |
563 |
Online |
Completed |
- Knoxville, Tennessee |
86 |
Online |
Completed |
- Wenatchee, Washington |
13 |
Online |
Completed |
- Molde, Norway |
84 |
Online |
Completed |
- Tydal, Norway |
50 |
Online |
Completed |
- Gedu, Bhutan |
100 |
Online |
Completed |
Total electrical capacity |
895 |
|
|
Pipeline capacity |
|
|
|
- Tydal, Norway Phase 1 |
40 |
In progress |
Q4 2024 |
- Tydal, Norway Phase 2 |
135 |
In progress |
Mid 2025 |
- Massillon, Ohio |
221 |
In progress |
Mid-to-late 2025 |
- Clarington, Ohio Phase 1 |
266 |
In progress |
Q3 2025 |
- Clarington, Ohio Phase 2 |
304 |
Pending approval |
Estimate 2026 |
- Jigmeling, Bhutan |
500 |
In progress |
Mid-Late 2025 |
- Rockdale, Texas |
179 |
In planning |
Estimate 2026 |
Total pipeline capacity |
1,645 |
|
|
Total global electrical capacity |
2,540 |
|
|
3 Indicative timing. All timing references are to calendar
quarters and years.
Upcoming Conferences and Events
- Sept. 5: Needham 4th Annual Virtual Crypto Conference
- Sept. 9 – 11: H.C. Wainwright 26th Annual Global Investment
Conference in New York City
- Nov. 14: Cantor Crypto, Digital Assets & AI Infrastructure
Conference in Miami
About Bitdeer Technologies Group
Bitdeer is a world-leading technology company
for blockchain and high-performance computing. Bitdeer is committed
to providing comprehensive computing solutions for its customers.
The Company handles complex processes involved in computing such as
equipment procurement, transport logistics, datacenter design and
construction, equipment management, and daily operations. The
Company also offers advanced cloud capabilities to customers with
high demand for artificial intelligence. Headquartered in
Singapore, Bitdeer has deployed datacenters in the United States,
Norway, and Bhutan. To learn more,
visit https://ir.bitdeer.com/ or follow Bitdeer on X @
BitdeerOfficial and LinkedIn @ Bitdeer Group.
Investors and others should note that Bitdeer
may announce material information using its website and/or on its
accounts on social media platforms, including X, formerly known as
Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages
investors and others to review the information it posts on the
social media and other communication channels listed on its
website.
Forward-Looking Statements
Statements in this press release about future expectations,
plans, and prospects, as well as any other statements regarding
matters that are not historical facts, may constitute
“forward-looking statements” within the meaning of The Private
Securities Litigation Reform Act of 1995. The words “anticipate,”
“look forward to,” “believe,” “continue,” “could,” “estimate,”
“expect,” “intend,” “may,” “plan,” “potential,” “predict,”
“project,” “should,” “target,” “will,” “would” and similar
expressions are intended to identify forward-looking statements,
although not all forward-looking statements contain these
identifying words. Actual results may differ materially from those
indicated by such forward-looking statements as a result of various
important factors, including factors discussed in the section
entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as
well as discussions of potential risks, uncertainties, and other
important factors in Bitdeer’s subsequent filings with
the U.S. Securities and Exchange Commission. Any
forward-looking statements contained in this press release speak
only as of the date hereof. Bitdeer specifically disclaims any
obligation to update any forward-looking statement, whether due to
new information, future events, or otherwise. Readers should not
rely upon the information on this page as current or accurate after
its publication date.
For investor and media inquiries, please
contact:
Investor RelationsOrange GroupYujia
ZhaiBitdeerIR@orangegroupadvisors.com
Public RelationsWachsmanBee Shinbitdeer@wachsman.com
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Oct 2024 to Nov 2024
Bitdeer Technologies (NASDAQ:BTDR)
Historical Stock Chart
From Nov 2023 to Nov 2024