Discontinued Operations. Under ASC 360, assets may be classified as held for sale even though discontinued operations classification is not met. The results of discontinued operations are reported in Net loss from discontinued operations, net of tax in the accompanying interim Condensed Consolidated Statements of Operations for current and prior periods, including any gain or loss recognized on closing or adjustment of the carrying amount to fair value less cost to sell. All other notes to these interim condensed consolidated financial statements present the results of continuing operations and exclude amounts related to discontinued operations for all periods presented.
Velardeña Properties
In December 2023, the Company restarted operations at the Velardeña Properties. In February 2024, it was determined that the initial performance of both the mine and the processing plant did not achieve the expected results. On February 29, 2024, the Company announced that it elected to discontinue operations at the Velardeña Properties and hold them for sale. Following that date, the Company shut down the Velardeña Properties and has held them for sale.
The Company previously announced the execution of certain asset purchase and sale agreements with a privately held Mexican company (the “Buyer”) to sell the Velardeña and Chicago mines, both oxide and sulfide processing plants and related equipment of the Velardeña Properties. Pursuant to the terms of the sale agreements, the Company agreed to sell certain mining concessions, equipment, land parcels and other assets in exchange for an aggregate purchase price of $5.5 million in cash, plus VAT. The terms of the sales agreement include completion and final payment of the sale by July 1, 2024.
There were four separate sales agreements. The first three sales agreements which include the combined sales of the Velardeña and Chicago mines, the sulfide processing plant and various related equipment were completed on June 20, 2024. The Company received payment in full of $2.5 million cash, plus VAT, and titles to the assets were transferred to the Buyer.
Velardeña Plant 2
The fourth agreement related to the sale of the Velardeña Properties covers the oxide plant and water wells (“Plant 2”), and the Buyer agreed to complete total payments of $3.0 million plus VAT on July 1, 2024. The Plant 2 agreement has not closed, and the Buyer is in default. In accordance with ASC 360, on June 30, 2024, the Company recorded an asset impairment charge of $411,000 in order to write down the remaining book value of Plant 2 to the salvage value which is equal to the amount received through June 30, 2024 from the Buyer of $373,000. Since June 30, 2024, the Buyer has continued to make periodic payments to the Company, and as of September 30, 2024, the Company has recorded deferred revenue of $1.0 million within Current liabilities held for sale on the interim Condensed Consolidated Balance Sheets. The Buyer has operational control of Plant 2, and we are no longer operating the property. We do not know whether or when the Buyer will make the remaining payments due. We are continuing to negotiate an extension of the agreement which would allow for the transfer of the title of Plant 2 to the Buyer and the Company would hold a mortgage to secure the payment. See Note 19.
Minera Labri
On August 28, 2024, the Company sold its wholly owned Mexican subsidiary, Minera Labri S.A. de C.V. (“Minera Labri”), to a private Mexican company for approximately $445,000. Minera Labri previously owned the Velardeña Properties’ sulfide plant, which together with the Velardeña mines, was sold to another privately held Mexican group earlier in 2024. Upon consummation of that transaction, Minera Labri held no assets but held net operating losses and inflation-adjusted capital contributions. Under Mexican law, the balance of Minera Labri’s capital contribution accounts (“CUCAs”) may be bought and sold.
Silex Argentina
On August 30, 2024, the Company entered into a binding letter agreement (the “Letter Agreement”) with Butte Energy Inc. (“Butte”) pursuant to which Butte would acquire 100% of the issued and outstanding shares of Silex Argentina S.A. (the “Silex Shares”), the Company’s wholly owned subsidiary that owns the El Quevar Project, located in Salta Province, Argentina (“El Quevar”). The Letter Agreement was binding on the Company and Butte, pending (i) negotiation of a definitive Acquisition Agreement (the “Acquisition Agreement”) on or prior to September 30, 2024, and (ii) closing of the sales transaction for the Silex Shares (the “Transaction”) on or prior to October 31, 2024. The purchase price of the